Questions
ayuda
option
My Daypo

ERASED TEST, YOU MAY BE INTERESTED ON70-633 Part 3

COMMENTS STATISTICS RECORDS
TAKE THE TEST
Title of test:
70-633 Part 3

Description:
Project Server

Author:
Mark
(Other tests from this author)

Creation Date:
22/12/2009

Category:
Computers

Number of questions: 45
Share the Test:
Facebook
Twitter
Whatsapp
Share the Test:
Facebook
Twitter
Whatsapp
Last comments
No comments about this test.
Content:
You work as a resource on a project at Certkiller.com. The project has been published to Microsoft Office Project Server 2007. Rory Allen, the project manager, wants a weekly status report on your task assignments. Amy Walsh, the resource manager also wants a weekly report of the hours you worked on your tasks. You must provide both managers with the required reports. What should you do? You should create a weekly status report in Microsoft Office Project Web Access. You should use the weekly timesheet to update progress in Microsoft Office Project Web Access. You should enter time in your timesheet and update your tasks on the My Tasks page in Microsoft Office Project Web Access. You should update the status of your tasks on the project plan in Microsoft Office Project Professional 2007.
You manage various projects that have been saved to Microsoft Office Project Server 2007. You have created a project custom field for status for your projects. You want to create a report of all Active and Completed projects in Microsoft Office Project Web Access. You want the report to include graphical display to indicate if the projects are within budget and schedule. What should you do? You should create a Project Center view in Microsoft Office Project Web Access. You should create a Data Analysis view in Microsoft Office Project Web Access. You should create a Team Tasks view in Microsoft Office Project Web Access. You should create a Resource Assignments view in Microsoft Office Project Web Access.
You manage several projects that were published to Microsoft Office Project Server 2007. You have created project custom fields for these projects. You want to use Microsoft Office Excel to view resource skill data and the data in the project custom fields. What should you do? You should open the Summary view for the Project Center page of Microsoft Office Project Web Access and export the grid to a Microsoft Office Excel worksheet. You should create a view on the Resource Center page of Microsoft Office Project Web Access and export the grid to a Microsoft Office Excel worksheet. You should open the Summary view on the Resources Center page of Microsoft Office Project Web Access and export the grid to a Microsoft Office Excel worksheet. You should create a view on the Data Analysis page of Microsoft Office Project Web Access and export the table to a Microsoft Office Excel worksheet.
You work as a project manager at Certkiller.com. You manage several projects that have been saved to Microsoft Office Project Server 2007. You need to create a view in Microsoft Office Project Web Access which displays the work performed by day for each project. The view must be filtered based on a customer custom field. What should you do? You should create a view on the Project Center page of Microsoft Office Project Web Access. The view should contain the customer custom field so that it can be filtered. You should create a view on the Project Center page of Microsoft Office Project Web Access. The view should contain the customer custom field, which must have Show Date and Time enabled. You should create a view which displays baseline work information by day and project with the customer custom field as a filter value on the Data Analysis page of Microsoft Office Project Web Access. You should create a view that displays actual work information by day and project with the customer field as a filter value on the Data Analysis page of Microsoft Office Project Web Access.
You want to provide project status view which includes key issues and risks, current tasks deliverables, and other project information. You want the project status view to appear on a single page in Microsoft Office Project Web Access. What should you do? You should alter the project workspace home page to include the relevant Web parts. You should provide hyperlinks to the relevant pages in an e-mail message. You should open the Project Center page in Microsoft Office Project Web Access. You should open the Project Details page in Microsoft Office Project Web Access.
Certkiller.com currently uses Microsoft Office Project Server 2007 to track project deliverables. You want to create a report that lists the total number of deliverables in Certkiller.com's entire project portfolio. What should you do? You should create a Data Analysis view in Microsoft Office Project Web Access. You should create a Project Center view in Microsoft Office Project Web Access. You should create a filter on any Project Center page in Microsoft Office Project Web Access. You should export the Deliverables grid on the projects' workspace sites to a Microsoft Office Excel worksheet.
You work as a project manager at Certkiller.com. You manage several projects that were published to Microsoft Office Project Server 2007. You have created a custom field for category which you use to group your projects by type. Your resource manager asks you for a view that indicates the type of project each resource has worked on over last six months. The view must be in the form of a bar chart. What should you do? You should create a Resource Center view in Microsoft Office Project Web Access. You should create a Resource Assignments view in Microsoft Office Project Web Access. You should create a Data Analysis view in Microsoft Office Project Web Access. You should create a Team Tasks view in Microsoft Office Project Web Access.
You work as a project manage at Certkiller.com. You are managing a project that has been saved to Microsoft Office Project Server 2007. You want to analyze the work performed on the project over the past 36 months. You want the information to be displayed in tabular form and you want it to be grouped by year, month, team and resource. What should you do? You should export the project's default Gantt view to a Microsoft Office Excel worksheet and combine the worksheets into a pivot table with the required fields. You should export the project's unsubmitted timesheets to a Microsoft Office Excel worksheet and combine the worksheets into a pivot table with the required fields. You should create a pivot chart with the required fields and save the pivot chart as an image on the Data Analysis page of Microsoft Office Project Web Access. You should create a pivot table with the required fields on the Data Analysis page of Microsoft Office Project Web Access and then export the table to a Microsoft Office Excel worksheet.
You work as a project manager at Certkiller.com. You manage several projects that have been saved to Microsoft Office Project Server 2007. You need to provide detailed information about individual resource utilization on all tasks in your projects. You also want to analyze all scheduled work for all project resources using Microsoft Office Project Web Access. What should you do? You should display the default Work view for each project on the Project Center page of Microsoft Office Project Web Access. You should create a pivot table with Work, RBS and Month fields of each project on the Data Analysis page of Microsoft Office Project Web Access. You should display the availability of the resources on all your projects on the Resource Center page of Microsoft Office Project Web Access. You should display the assignments of the resources on each project on the Resource Center page of Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. You manage several projects that have been saved to Microsoft Office Project Server 2007. Your projects have several risks that are associated with them. You are required to display the status of all risks associated with your projects. What should you do? You should create a view of the risks list and filter it to display only items with your name in the Owner field on the project workspace site. You should create a view of the risks list and filter it to display only the items with your name in the Assigned To field on the project workspace site. You should display the Issues and Risks page in Microsoft Office Project Web Access. You should create a risks list and add the associated risks Web part to the home page of the project workspace site.
You work as a project manager at Certkiller.com. You are managing a project that has been saved to Microsoft Office Project Server 2007. You have created a contingency plan for a risk which has been created and associated with a task in your project. You want the contingency plan to be displayed whenever anyone views the risk. What should you do? You should create a risks list that includes the contingency plan in Microsoft Office Project Web Access. You should update the risk item with the contingency plan in Microsoft Office Project Web Access. You should create a new activity which includes the steps of the contingency plan in Microsoft Office Project Web Access. You should document the contingency plan on the task associated with the risk in Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. You made use of the Risks lists in Microsoft Office Project Web Access to identify and log risks associated with your projects. You want to assign risks to resources that will own the risk and mitigate it until the risk is closed. You want a reminder to appear on the Home page of the resource to whom the risk is assigned. What should you do? You should specify the resource name in the Owner field in Microsoft Office Project Web Access. You should specify the resource names in the Assigned To field in Microsoft Office Project Web Access. You should specify the resource name in the Mitigation field in Microsoft Office Project Web Access. You should link the risk to a task that has already been assigned to the resource.
You work as a project manager at Certkiller.com. You are currently managing a project that has been saved to Microsoft Office Project Server 2007. The project has a risk that is associated to several tasks that have already been defined. You have identified additional tasks that must be added to the project. These tasks will also have the associated risk. You must be able to use Microsoft Office Project Web Access to track this risk for the new tasks. What should you do? You should specify yourself as the owner of the risk. You should create a new link from the existing risk to the new tasks. You should create a new risk of the same category as the existing risk and link the new risk to the new tasks. You should create a new issue of the same category as the existing risk and link the issue to the new tasks.
You work as a project manager at Certkiller.com. You are managing a project that has been published to Microsoft Office Project Server 2007. An issue associated with several tasks in your project has changed. You want to update the issue on the project workspace site. What should you do? You should delete the existing issue and create a new issue with the updated information. You should create a new risk and link the risk to the existing issue. You should edit the existing issue. You should create a new issue with the updated information and link the new issue to the existing issue.
You work on a project that has been published to Microsoft Office Project Server 2007. The project has a risk associated with a task that requires imported machinery. You are informed that the importer of the machinery does not have stock and that the expected time of arrival (ETA) of the machinery is two weeks in the future. You want to escalate this risk to an issue without losing the historical record of the risk in Microsoft Office Project Web Access. What should you do? You should assign the risk to the project manager. You should create an issue and link the issue to the risk. You can then close the risk. You should create an issue that contains the risk information and delete the risk. You should add the task to the hot issues section of you status report and then submit the report.
You work as a project manager at Certkiller.com. You are managing a project that has been saved to Microsoft Office Project Server 2007. The project has a risk associated with a task that requires the use of an important piece of machinery. The machinery fails and needs to be replaced immediately. You want to create an issue that ensures that someone is clearly accountable for responding to the problem. What should you do? You should create a new Issue Tracking list in Microsoft Office Project Web Access. You should create a new Issue Tracking list on the project workspace site. You should add an Issues Web part to the page on the project workspace site. You should add a new issue to the Issues list on the project workspace site.
You work as a project manager at Certkiller.com. You are managing a project that has been published to Microsoft Office Project Server 2007. The project has a risk associated with a task that requires an imported piece of machinery. The machinery fails and the importer of the machinery does not have more stock of the machinery. While you are waiting for the machinery to be replaced, the deadline for the tasks passes. You now want to create a new issue and associate the new issue with the project plan. What should you do? You should link the issue to the risk associated with the task in Microsoft Office Project Web Access. You should link the issue to an existing issue in Microsoft Office Project Web Access. You should link the issue to the resource assigned to the task in Microsoft Office Project Web Access. You should link the issue to the task in Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. You have just published a project to Microsoft Office Project Server 2007. You want to track risks associated with tasks in the project but the project has no project workspace site. You now want to create a project workspace site for your project. What should you do? You should select a project workspace template in server settings of Microsoft Office Project Web Access. You should select the Automatic provisioning mode in server settings of Microsoft Office Project Web Access. You should edit the project and select Save Workspace on the Project Center page of Microsoft Office Project Web Access. You should edit the project, publish it, and select the option to create a project workspace site on the Project Center page of Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. You want to add a few deliverables to project tasks of a project schedule that you have created and saved in Microsoft Office Project Professional 2007. You discover that the Manage Deliverables feature is not available. You need to add the deliverables to the project. What should you do? You should publish the project plan and select the option to create a project workspace site. You should save the project plan as a project workspace. You should save the project plan to a project workspace site. You should make use of the Manage Dependencies on Deliverables feature.
You work as a project manager at Certkiller.com. You are managing a project that has been published to Microsoft Office Project Server 2007. You want to be notified when team members add documents to the Deliverables library of the project workspace site. You want to configure Microsoft Office Project Web Access to automatically send you notifications whenever new documents are added to the Deliverables library. What should you do? You should create an alert for new items in the Deliverables library. You should modify the notification options on the Manage My Alerts and Reminders page. You should modify notification options on the My Resources Alerts and Reminders page. You should subscribe to the Really Simple Syndication (RSS) feed of the Deliverables library.
You work as a project manager at Certkiller.com. You are managing a project that has been saved to Microsoft Office Project Server 2007. The project stipulates that Certkiller.com will make fixed payments of $15,000 to a subcontractor as soon as each deliverable is approved. Each deliverable requires multiple tasks. You want to use Microsoft Office Project Web Access to track these fixed payment costs and include the payments in the project costs. What should you do? You should create a Work resource with a standard rate of $15,000 per unit. Then assign the resource to project tasks that are dependent on the deliverable. You should create a Work resource with a standard rate of $15,000 per use. Then assign the resource to project tasks that are dependent on the deliverable. You should create a milestone task for each deliverable in the project plan. Then assign a local Work resource with a cost of $15,000 per use to the milestone tasks. You should create an item in the Deliverables list for each deliverable and add a note in the Description field that states that each deliverable costs $15,000.
You work as a project manager at Certkiller.com. A program manager named Rory Allen uses Microsoft Office Project Professional 2007 to create a program schedule with a Deliverables list for key milestones in one of your projects. You want to display the differences between dates for program milestones and project milestones when they change. What should you do? You should copy Rory Allen's program milestones to the Deliverables list of the project workspace site. You should manage dependencies on deliverables and link the deliverables to their associated tasks. You should manage dependencies on deliverables without linking the deliverables to tasks. You should insert the project and program schedule into a master project. Then you should create start-to-finish dependencies between tasks for project and program milestones.
You work as a project manager at Certkiller.com. You are managing several projects that have been published to Microsoft Office Project Server 2007. Each of these projects has numerous linked deliverables. You want to determine how many and which deliverables are due each day for the next four months. What should you do? You should create a master project that includes all your projects and select the Manage Dependencies on Deliverables option in Microsoft Office Project Professional 2007. You should create a master project that includes all your projects and select the Manage Deliverables option in Microsoft Office Project Professional 2007. You should create a Data Analysis view in Microsoft Office Project Web Access. You should create a Project Details view that includes the Deliverable Finish field in Microsoft Office Project Web Access.
Certkiller.com develops products that are dependent on several projects that are published in Microsoft Office Project Server 2007. These products have several defined milestones in its development life cycle. You must ensure that project managers can view the life-cycle milestones in their project schedules and compare them with the project start and finish milestones in Microsoft Office Project Web Access. What should you do? You should create a deliverable. You should create an event. You should create an announcement. You should create a Milestones list.
You work as a project manager at Certkiller.com. You have created and published a project plan to Microsoft Office Project Server 2007. Your project plan is dependent on the completion of a deliverable in another project plan. You are informed that the deliverable has been delayed. You want to display the new dates of the deliverables in the Gannt Chart view. You also want to revise the dates of your project plan. What should you do? You should add a new dependency to your project plan and rebaseline the plan. You should add a new dependency to your project plan and reschedule the project plan to start after the completion of the deliverable. You should accept all server changes and rebaseline the project plan. You should accept all server changes and reschedule the project plan to start after completion of the deliverable.
You work as a project manager at Certkiller.com. You are managing a project that has been saved to Microsoft Office Project Server 2007. The project has multiple deadlines. You discover that the Gantt Chart views on the Project Details page do not show deadlines. You want to display a Gantt chart with project deadlines but you do not want change any views that are used by other Certkiller.com users. What should you do? You should create a new view that uses the Gannt format for the Project Center page in Microsoft Project Web Access. You should create a new view that uses a new Gannt Chart format for the Project Center page in Microsoft Project Web Access. You should create a new view that uses the Gannt Chart format for the Project Details page in Microsoft Project Web Access. You should display the project plan in the Task Sheet view in Microsoft Office Project Professional 2007.
You work as a project manager at Certkiller.com. You manage two projects that have been published to Microsoft Office Project Server 2007. The two projects have deliverables and resources assigned to the tasks. A task in Project2 is dependent on a task in Project1. You want to create a link between the two projects that will ensure that the task in Project2 will not start before a task in Project1 is completed. What should you do? You should open the Assignment Details page for the task in Project2 in Microsoft Office Project Web Access and set the start date for the task to the finish date of the task in Project1. You should open the Assignment Details page for the task in Project2 in Microsoft Office Project Web Access and expand Related Assignments. Then set the task from Project1 as a predecessor. You should use the Manage Dependencies on Deliverables command in Microsoft Office Project Professional 2007 to link the task in Project2 to a deliverable in Project1. You should link the task from Project1 and the task from Project2 in Microsoft Office Project Professional 2007.
You work as a Project Manager at Certkiller.com. The enterprise projects that you manage are saved to Microsoft Office Project Server 2007 while your local projects are saved on a client computer named CERTKILLER-WS633. You use Microsoft Office Project Professional 2007 when working on local projects. However, when you start Project, the project connects automatically to Project Server. You want to configure Project so that you can operate in both modes. What should you do? You should create a new Project Server account in Project. You should use Microsoft Office Project Server 2007 for local projects. You should reconfigure Project to automatically set the connection to Project Server. You should reconfigure Project and manually set the connection to Project Server.
You work as a Project Manager at Certkiller.com. Certkiller.com runs multiple instances of Microsoft Office Project Server 2007 that run on various server computers. Microsoft Office Project Professional 2007 runs on your client computer that is named CERTKILLER-WS633. Multiple accounts have been created on your client computer and have been configured to log on automatically with the default account. You want to determine which account you are currently using on CERTKILLER-WS633. What should you do? You should use the Project Server Accounts dialog box to configure one of the Microsoft Office Project Server 2007 servers as the default server. You should use the Project Server Accounts dialog box to determine the current server. You should use open the project plan and determine if any tasks have been completed. You should use the Help menu to open About Microsoft Office Project and determine the current server.
You work as a Project Manager at Certkiller.com. A Certkiller.com user named Rory Allen has been assigned to assist you with a project plan that has been saved to Microsoft Office Project Server 2007. You are currently working at Rory Allen's client computer, which is named CERTKILLER-WS633. You need to add resources to the project plan; however, Rory Allen does not have the required permissions to perform this task. What should you do? You should use Microsoft Office Project Web Access to change Rory Allen's personal settings. You should use Microsoft Office Project Web Access and sign in using your own credentials on the Welcome menu. You should use Microsoft Office Project Web Access and enter your name as the Name value on the User Information page. You should use Microsoft Office Project Web Access and deselect the always follow Web settings on the Regional Settings page.
You work as a project manager at Certkiller.com. Certkiller.com is to hire a new resource that will be assigned to one of your projects. You want to assign the new resource to a task. However, Certkiller.com's security policy requires that all resources must use Windows Authentication to access Microsoft Office Project Server 2007. What should you do? Request that the Project Server administrator to add the new resource to the enterprise pool but not to allow the resource to log on to Microsoft Office Project Server 2007 until a Windows account has been created for the resource. Request that the Project Server administrator to add the new resource to the Resource Center and to allow the resource to log on to Microsoft Office Project Server 2007 using Forms Authentication until a Windows account has been created for the resource. Request that the Project Server administrator to add a new user to the Manage Users page and to allow the new user to be assigned to a resource. Request that the Project Server administrator to add a new user to the Manage Users page and to allow the new user to be assigned to a task.
You work as an Administrator at Certkiller.com. A user named Amy Walsh is employed as a Project Manager at Certkiller.com. Amy Walsh reports that she cannot use Microsoft Office Project Web Access to alter the tracking method of a project that she published to Microsoft Office Project Server 2007. Amy Walsh informs you that she created the project in Microsoft Office Project Professional 2007. You need to ensure that Amy Walsh can alter the tracking method for the project. What should you do? Make Amy Walsh a member of the Resource Managers group. Make Amy Walsh a member of the Portfolio Managers group. Reconfigure the time tracking option to allow project managers to select tracking methods. Reconfigure the time tracking option to use the tracking method that Amy Walsh requires.
You work as a project manager at Certkiller.com. The default tracking method for all projects is set to percent complete and all projects are saved to Microsoft Office Project Server 2007. You need to create a new project where the tracking method must be based on total actual work. You have permission to change the tracking method for the project but you do not want to affect the tracking method of the other projects. What should you do? You should use Microsoft Office Project Web Access to set the Project Server default tracking method to percent complete. You should use Microsoft Office Project Web Access to set the Project Server default tracking method to actual hours and remaining work. You should use Microsoft Office Project Professional 2007 to set the collaboration options for the project to actual hours and remaining work. You should use Microsoft Office Project Professional 2007 to set the collaboration options for the project to percent complete.
You work as a project manager at Certkiller.com. You use Microsoft Office Project Server 2007 to create a new project plan. You do not want to allow resources to reassign tasks in this project plan. What should you do? You should set the collaboration options for the project plan to prevent resources from reassigning tasks. You should set the global permissions for the project plan to prevent resources from reassigning tasks. You should set the resource assignments for the project plan to Demand on the Assign Resources page. You should use the Build Team from Enterprise feature to set the resource assignments for the project plan to Committed.
You work as a project manager at Certkiller.com. You are working on a project that has been saved to Microsoft Office Project Server 2007. The project status is currently set to Proposed in the custom field. You want to change the project status to Active. What should you do? You should use Microsoft Office Project Web Access and set the custom field for project status to Active on the Project Center page. You should use Microsoft Office Project Web Access and set the set the booking type for the project resources to Committed. You should create a status column with a default value of Active in the Deliverables list of the project workspace site. You should create a status column with a default value of Active in the Project Documents library of the project workspace site.
You work as a project manager at Certkiller.com. Last week you modified a few Web parts of a project workspace site using Microsoft Office Project Web Access. You want to restore the Web parts to their original appearance without losing content. What should you do? You should compare the layout view with an unaltered project workspace site in Microsoft Office Project Web Access and remove any additional Web parts. You should compare the layout view with an unaltered project workspace site in Microsoft Office Project Web Access and add Web parts that are missing. You should compare the layout view with an unaltered project workspace site in Microsoft Office Project Web Access and rearrange the Web parts. You should set the Look and feel site setting to Reset to site definition in Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. . You are working on a project that has been published to Microsoft Office Project Server 2007. You have configured e-mail notification to send you an alert when a resource submits a status report. You want to disable e-mail notification without losing any submitted status reports. What should you do? You should notify resources not to send an e-mail notification when they submit a status report. You should use Microsoft Office Project Web Access to delete the current status report request and create a new status report request without configuring e-mail notification. You should use Microsoft Office Outlook and modify your mail synchronization settings. You should use the Personal Settings page of Microsoft Office Project Web Access to modify your notification options.
You work as a project manager at Certkiller.com. You are using Microsoft Office Project Professional 2007 on a client computer named CERTKILLER-WS633 to manage a project. You need to connect to Microsoft Office Project Server 2007 to add resource to the project from the enterprise resource pool. What should you do? You should change the settings on the Properties page in Project. You should add yourself as a resource to the project plan in Project. You should create a new Project Server account in Enterprise Options in Project. You should create a new user on the Resource Center page of Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. You are working on a project that has been published to Microsoft Office Project Server 2007. You want to receive e-mail notification when a resource submits a status report. What should you do? You should configure synchronization with Microsoft Office Outlook in Microsoft Office Project Web Access. You should configure notification options on the Personal Settings page of Microsoft Office Project Web Access. You should configure fixed timesheet approval routing in Microsoft Office Project Web Access. You should configure timesheet auditing in Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. Your duties include the management of various project documents. Each document has different properties. You want to organize the documents so that they can be filtered by property. What should you do? You should create a folder for each property. You should create a document library for each property. You should create a Web site for each property. You should create a column for each property.
You work as a project manager at Certkiller.com. You are responsible for managing several projects that are saved to Microsoft Office Project Server 2007. Several of your projects are in the planning phase. Assignments for these projects are not displayed on the My Tasks page for resources in Microsoft Office Project Web Access. You want to list all projects that have assignments that are not displayed on the My Tasks page for resources in Microsoft Office Project Web Access. What should you do? You should access the list of projects from the Project Server Published Store in Microsoft Office Project Professional 2007. You should access the list of projects from the Proposals and Activities page of Microsoft Office Project Web Access. You should access the list of projects from the Project Server Working Store in Microsoft Office Project Professional 2007. You should access the list of sites and workspaces in Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. Certkiller.com uses Microsoft Office Project Server 2007 to manage its projects. Certkiller.com has several enterprise custom fields for products that are associated with its projects. You want all Certkiller.com project managers to use a custom view that includes the enterprise custom fields for products when they create new project plans. What should you do? You should create a blank project with a custom view that includes the enterprise custom fields for products. You can then save the project as an Enterprise template. You should add the enterprise custom fields for products to the project managers' projects. You should add the enterprise custom fields for products to your project workspace template. You should create a custom view that includes the enterprise custom fields for products in the Enterprise Global template.
You work as a project manager at Certkiller.com. Certkiller.com uses an enterprise template that has been saved to Microsoft Office Project Server 2007. A project manager named Rory Allen reports that the template does not calculate time estimates correctly. You want to rectify the problem and update the enterprise template without duplicating the template file. What should you do? You should use the enterprise template to create a new project. You can then rectify the error and save the project as a project plan. You should use the enterprise template to create a new project. You can then rectify the error and save the project as the enterprise template, using a new file name. You should use the enterprise template to create a new project. You can then rectify the error and save the project as the enterprise template, using the same file name. You should use a blank template to create a new project. You can then recreate the project plan without the error and save the project as the enterprise template, using the same file name.
You work as a project manager at Certkiller.com. One of your projects that has been saved to Microsoft Office Project Server 2007 is assigned to a new project manager named Rory Allen. You need to make Rory Allen the owner of this project plan. What should you do? You should change the Properties sheet for the project plan file in Microsoft Office Project Professional 2007. You should change the Project Information field for the project plan in Microsoft Office Project Professional 2007. You should change the properties of the project on the Project Center page of Microsoft Office Project Web Access. You should add Rory Allen as the manager of the project on the Resources Center page of Microsoft Office Project Web Access.
You work as a project manager at Certkiller.com. You want to create a project plan template that will be used to estimate budget and resource requirements for future projects that will published to Microsoft Office Project Server 2007. You do not want named resource assignments to be affected when projects are created with this template. What should you do? You should use generic resource assignments when creating the template. You should use named committed resource assignments when creating the template. You should use committed resource assignments when creating the template. You should leave the Resource Name field blank when creating the template.