Content:
Where do you control whether a project stock is managed as valuated or non-valuated project stock? In the material master In the network activity In the WBS element In the project definition.
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element? Activity allocation Claculation of actual values Goods receipt for purchase orders Creation of purchase orders.
Which of the following statements apply to project versions? There are 2 correct answers. Manually created project versions always require a project version profile Project versions can be changed Project versions are mandatory for Milestone Trend Analysis (MTA) Project versions can be created automatically based on user status.
Which statement is valid regarding networks? There are 2 correct answers. A network activity can be assigned to several WBS elements Relationships can be used to connect activities of different networks Material components can be assigned to activity elements A network can be activity-account-assigned and header-account-assigned.
Which object is relevant in assembly processing to create an assembly order for the SD document? Requirement class Project profile Item category Control key.
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates? The table of MRP conttrollers The network profile The control key The scheduling parameters for the network.
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? There are 2 correct answers. Purchase order items Internal orders Reservations Sales order items.
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget? Hierarchial report on budget updates Structure overview for budgets Cost element report on budget updates Line item report for budgets.
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason? Please choose the correct answer. The normal duration of each activity is missing There is a loop in the network The control key is set to no scheduling The scheduling type is set to capacity requirements only.
You want to use billing for a customer project. Which customizing object controls the billing of sales order items? Please choose the correct answer. Requirements type Items category Schedule line category Requirements class.
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing fields do you use? Please choose the correct answer. Project profile Network profile Data entry profile Network type.
Which of the following is visible in the project planning board? There are 2 correct answers to this question. Production orders assigned to WBS elements Maintenance orders assigned to an activity Capacity requirements Project-relevant purchase orders.
You want to assign milestones to WBS elements. For what can you use the milestones? There are 2 correct answers to this question. To transfer the actual date to the billing plan To set an actual finish date for the WBS elements For trend analysis To start workflow tasks.
What are the prerequisites for resource-related billing? There are 2 correct answers to this question. An activity-account-assigned network that is assigned to a sales order item Released WBS elements, activities, and/or activity elements A dynamic item processor (DIP) profile with the appropriate settings A header-account-assigned network that is assigned to a sales order item.
Float time is calculated during scheduling. Which of the following statements about float time are correct? There are 2 correct answers to this question. By default, critical activities have a float time, which is less than or equal to zero Activities with the time constraint "Must start on" always have a negative float time. Float time can be negative The maximum size of a free float is as large as the totalt float of an activity. The float time of WBS elements is calculated by extrapolation.
To which object can you assign a factory calendar? Milestone Material component Network header Relationship.
Which of the following data can be maintained in a standard network? There are 3 correct answers to this question. Relationships Basic dates for activities Internally processed activities Document information records Material components.
Which of the following factors influence the scheduling of internal processing activities? There are 3 correct answer to this question. The unit (for example, hour day) of the field Normal Duration field of the activity An activated Scheduling indicator in the control key of the internal processing activity Whether the work for the internal activity is greater than its duration The factory calendar in the work center used for the internal processing activity The relationships between activity elements.
A customer needs to analyzed the capacity requirements of their network activities. Which reports do you recommend? Structure information system reports Resource reports Hierarchial reports Cost element reports .
Which report can use user-specific layouts? Please choose the correct answer. Hierarchial report Cost element report Line item report Enhanced individual overview.
Which object is used to alloacte the costs form a claim to the project sturcture? WBS element Claim Network activity Internal order.
Most of the reports in SAP Project Systems can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data? Reports by cost element Individual Overviews Structure Overview Hierarchial Reports.
Where can you define a network as "header-account-assigned" or "activity-account-assigned? Network profile Network type Project profile Parameters for the network type.
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain? Basic dates of the WBS Basic dates of the network activity Forecast dates of the WBS Actual dates of the network capacity.
Where can you assign the user status profile for WBS elements? There are 3 correct answers to this question. In the project version In the project definition of a standard WBS In the operative WBS element In the project type In the project profile.
You are working with predefined project coding masks to create projects. Which of the following statements apply? There are 2 correct answers to this question. You can use the same coding mask for standard projects and operative projects You can use an indicator to determine that only coded project numbers may be used within SAP Project System You can only use numbers for a project coding mask definition You can shorten the project mask even when there are existing projects.