SAP Active 24_03
|
|
Title of test:
![]() SAP Active 24_03 Description: SAP Active 24_03 |



| New Comment |
|---|
NO RECORDS |
|
SAP Activate Methodology Foundation and Tools 1 of 80 What is the correct phase order of an SAP Activate project?. Prepare > Explore > Realize > Deploy > Run. Prepare > Explore > Discover > Realize > Deploy. Discover > Prepare > Explore > Realize > Deploy > Run. Prepare > Discover > Explore > Realize > Deploy > Run. Workstreams Overview 2 of 80 Which steps should you perform while preparing for a fit-to-standard analysis in an SAP Data Warehouse Cloud project? Note: There are 2 correct answers to this question. Review Cutover Plan accelerator in the Data Management workstream. Review all the necessary Implementation Design Principles (IDPs). Review SAP S/4HANA Cloud best practices availability for your country. Review all the necessary leading practice process diagrams. Transition Path "New Implementation SAP S/4HANA on premise" 3 of 80 When deploying SAP S/4HANA Cloud, private edition using new implementation, which of the following is recommended to code custom developments? Note: There are 2 correct answers to this question. SAP Business Technology Platform. SAP Best Practices. SAP ABAP Workbench. SAP Support Portal. Agile Project Planning 4 of 80 "Comparing the SAP Activate methodology with Waterfall, what activities are performed by the new project roles?". ( ) Scrum master to prepare the project plan. ( ) Scrum master and project sponsor to define project charter. ( ) Product owner to discuss schedule with the customer. ( ) Scrum team to review best practices. Workstreams Overview 5 di 80 "You are defining the testing strategy for your project. What would you include in a Scope of Integration test? Note: There are 2 correct answers to this question.". The functionality of end-to-end business processes. The connectivity with other systems. The connectivity between database and application servers. The procedures for data migration. Introduction to SAP Activate 6 of 80 Which of the following are SAP Activate workstreams? Note: There are 2 correct answers to this question. [ ] Change Management. [ ] Data Migration. [ ] Extensibility. [ ] Project Management. Transition Path "System Conversion" and "Selective Data Transition" 7 of 80 What tool provides sizing estimations for the "System Conversion" transition path?. ( ) SAP Digital Discovery Assessment. ( ) SAP Business Accelerator Hub. ( ) SAP Readiness Check. ( ) SAP Transformation Navigator. Workstreams Overview 8 of 80 What can you find in the SAP Fiori apps reference library? Note: There are 3 correct answers to this question. Shortcut to the Quicksizer tool to estimate hardware requirements. Related app recommendations based on your usage profile. Shortcut to the Maintenance Planner tool to establish the technical update path. Related app-specific solution design guidelines ( Related app-specific SAP Fiori design guidelines.). Installation and configuration requirements for selected apps. Transition Path "New Implementation SAP S/4HANA Cloud, public edition" 9 of 80 Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path?. ( ) Fit-to-standard. ( ) Solution Validation and Delta Design. ( ) Request SAP S/4HANA Cloud Development System. ( ) Develop and document Enablement Strategy. Agile Project Planning 10 of 80 Which of the following considerations apply when determining the project methodology? Note: There are 3 correct answers to this question. [ ] Integration fit. [ ] Readiness fit. [ ] Project Manager fit. [ ] Project fit. [ ] Organizational fit. Transition Path "New Implementation SAP S/4HANA on premise" 11 of 80 Which of the following is the customer's responsibility in both on-premise and private cloud scenarios?. Middleware. Servers. Database. Operating system. Workstreams Overview 12 of 80 Which SAP products relate to the scenarios included in the SAP Activate roadmap for the Intelligent Enterprise? Note: There are 3 correct answers to this question. SAP Sales Cloud. SAP Fieldglass. SAP S/4HANA Cloud. SAP Concur. SAP Integrated Business Planning for Supply Chain. Agile Project Planning 13 of 80 What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question. Prioritize backlog user stories by business priority. Define objectives for each release. Analyze the functional and technical dependencies between user stories. Estimate the backlog user stories. Introduction to SAP Activate 14 of 80 When applying a cloud mindset in a greenfield implementation, which of the following should you consider? Note: There are 2 correct answers to this question. Use quality gates. Use supported extensibility technologies. Ensure transparency on deviations. Use SAP Digital Discovery Assessment. Agile Project Delivery 15 of 80 What criteria does the product owner use to sequence the backlog? Note: There are 2 correct answers to this question. Technical dependencies. Duration of the sprint. Business priority. Complexity of the story. Workstreams Overview 16 of 80 For which of the following products do you find a specific set of SAP Best Practices for the public sector?. SAP SuccessFactors Employee Central. SAP Ariba Supplier Management. SAP S/4HANA Cloud, public edition. SAP S/4HANA. Agile Project Delivery 17 of 80 What is the objective of using scaling Scrum techniques when coordinating large teams in complex projects?. To bring all specialists, such as the company legal advisors, into the scrum team. To ensure alignment in architecture, configuration, and integration. To reallocate staff to skill-based teams such as developers in one single team. To manage the flow of information between the project and stakeholders. Agile Project Planning 18 of 80 When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?. Release plan and sprint ceremony guidelines should be finalized. Realize phase scope, planning, and budget should be completed and final. Sprint planning and sprint durations should be defined for the first 2 to 3 sprints. User stories on product backlog should be in ready state for the first 2 to 3 sprints. Agile Project Planning 19 of 80 Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?. Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity. Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team. Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks. Product Owner’s relative effort estimate that will be needed to implement and test the user story. Introduction to SAP Activate 20 of 80 Which of the following is used to perform configuration in SAP S/4HANA Cloud, private edition?. Self Service Configuration UIs (SSCUI)s. SAP Solution Manager. SAP Central Business Configuration. IMG (Implementation Guide). Workstreams Overview 21 of 80 In which workstream do you execute an organizational change impact analysis?. Solution Adoption. Analytics. Project Management. Application Design and Configuration. Transition Path "New Implementation SAP S/4HANA Cloud, public edition" 22 of 80 What is the difference between the "New Implementation of SAP S/4HANA Cloud, public edition" and the "New Implementation of SAP S/4HANA Cloud, private edition" transition paths? Note: There are 2 correct answers to this question. SAP S/4HANA Cloud, private edition is only available through SAP Cloud services and with embedded implementation services from SAP. Upgrades of SAP S/4HANA Cloud, public edition are based on SAP timelines, and upgrades of SAP S/4HANA Cloud, private edition are based on timelines agreed between SAP and the customer. SAP S/4HANA Cloud, private edition uses the Implementation Guide (IMG) and SAP S/4HANA Cloud, public edition uses SAP Central Business Configuration. SAP S/4HANA Cloud, public edition does NOT offer built-in capabilities for extensibility, while SAP S/4HANA Cloud, private edition offers a full development environment. Transition Path "Private and Public Cloud" 23 of 80 Which of the following tools facilitate secure communication between SAP cloud solutions and protected on-premise networks that cannot be accessed directly from the Internet?. ○ Identity Authentication service. ○ SAP Build Code. ○ Cloud Integration Automation service. ○ SAP BTP Connectivity service. Workstreams Overview 24 of 80 Which additional scope options does the strategic advisory service for cloud analytics offer? Note: There are 2 correct answers to this question. ☐ Baseline package. ☐ SAP Activate methodology for SAP Datasphere. ☐ SAP S/4HANA for Central Finance. ☐ Extended package. Introduction to SAP Activate 25 of 80 Which of the following characteristics relate to the Focused Build for SAP Solution Manager functionality? Note: There are 2 correct answers to this question. SAP delivers all configuration values within your project. SAP delivers a standard solution without any additional coding required. SAP delivers a standard solution with its own separate license. SAP delivers all knowledge required with the solution. Agile Project Delivery 26 of 80 When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?. During the sprint backlog review. During the sprint user acceptance test. During the sprint retrospective. During the sprint review. Transition Path "System Conversion" and "Selective Data Transition" 27 of 80 What is the preferred option to migrate to SAP S/4HANA Cloud, private edition while keeping most of the original processes and add a new configuration?. ( ) Mix and Match. ( ) New Implementation. ( ) System Conversion. ( ) Shell Conversion. Workstreams Overview 28 of 80 Which of the following best outlines the sequence of testing in the Realize phase?. String Test Integration Test User Acceptance Test. Integration Test User Acceptance Test String Test. Data Migration String Test User Acceptance Test. String Test User Acceptance Test Integration Test. Transition Path "New Implementation SAP S/4HANA on premise" 29 of 80 From which platform are you able to deploy a trial system within a short timeframe?. ( ) SAP Support Portal. ( ) SAP Learning Hub. ( ) SAP Cloud Appliance Library. ( ) SAP Business Technology Platform. Transition Path "System Conversion" and "Selective Data Transition" 30 of 80 A customer with an existing SAP S/4HANA solution is exploring the best approach to move without change their landscape into the cloud. Which is the most suitable option for the customer?. ( ) Lift and Shift. ( ) Mix and Match. ( ) Selective Data Transition. ( ) System Conversion. Transition Path "System Conversion" and "Selective Data Transition" 31 of 80 Which of the following are capabilities of SAP Landscape Transformation Tool used in Selective Data Transition scenarios?. Full set of historical transactional data. Consolidation of systems. Migration of business units. Migration of selected applications. Configuration of open backlog items. SAP Activate Methodology Foundation and Tools 32 of 80 Which of the following Accelerators can you find in the SAP Signavio Process Navigator? Note: There are 2 correct answers to this question. Test Script. Process Diagram. Stakeholder Identification Guide. Data Migration plan. Transition Path "New Implementation SAP S/4HANA Cloud, public edition" 33 of 80 What accelerator can help you document the configuration definition in the Explore phase?. ◯ Backlog template. ◯ Change request template. ◯ Data definition template. ◯ Test plan template. Transition Path "System Conversion" and "Selective Data Transition" 34 of 80 Your customer is using a non-SAP ERP system and decides to deploy SAP S/4HANA. Which of the following options are available to your customer? Note: There are 3 correct answers to this question. ☐ New Implementation SAP S/4HANA Cloud, private edition. ☐ System Conversion SAP S/4HANA. ☐ System Conversion SAP S/4HANA Cloud, private edition. ☐ New Implementation SAP S/4HANA. ☐ New Implementation SAP S/4HANA Cloud, public edition. Transition Path "New Implementation SAP S/4HANA on premise" 35 of 80 Which of the following capabilities does test management in SAP Cloud ALM for Implementation provide? Note: There are 2 correct answers to this question. ☐ Load and Volume Testing. ☐ Manual and Automated Testing. ☐ Test Data Container. ☐ Test Plans. SAP Activate Methodology Foundation and Tools 36 of 80 Which of the following are workshop design principles/guidelines? Note: There are 2 correct answers to this question. [ ] Active participation. [ ] Expert configuration definitions. [ ] Validation by end users. [ ] Fit-to-standard. Introduction to SAP Activate 37 di 80 "What is the primary purpose of the SAP Activate methodology?". To provide end-to-end application lifecycle management (Fornire la gestione del ciclo di vita delle applicazioni end-to-end). To enable access to the SAP ecosystem (Abilitare l'accesso all'ecosistema SAP). To manage project documentation (Gestire la documentazione di progetto). To expedite all deployments of SAP products (Accelerare tutte le implementazioni dei prodotti SAP). Introduction to SAP Activate 38 di 80 Testo della domanda: Which tool do you use to configure SAP S/4HANA Cloud, public edition?. ( ) IMG (Implementation Guide). ( ) SAP Central Business Configuration. ( ) SAP Solution Manager. ( ) SAP Cloud ALM. Transition Path "Private and Public Cloud" 39 di 80 Testo: "What are the two common approaches to Selective Data Transition adopting RISE with SAP? Note: There are 2 correct answers to this question.". [ ] Mix and Match. [ ] Fit-to-standard. [ ] System Conversion. [ ] Shell Conversion. "New Implementation SAP S/4HANA Cloud, public edition" 40 di 80 Testo della domanda: "Which of the following characteristics are mandatory with SAP S/4HANA Cloud, public edition? Note: There are 2 correct answers to this question.". [ ] Software upgrades performed by SAP. [ ] Choice of hardware vendor. [ ] Customer data center deployment. [ ] Activation of SAP Best Practices. Agile Project Delivery 41 of 80 What is the purpose of the scrum board?. ○ To visualize the resource load. ○ To visualize team progress. ○ To visualize the resource load. ○ To show readiness of the release. ○ To document the results of the fit-to-standard workshop. SAP Activate Methodology Foundation and Tools 42 of 80 Which functionality is available in Focused Build?. ○ Integration Monitoring. ○ Test Management. ○ User Experience Monitoring. ○ Custom Code Management. SAP Activate Methodology Foundation and Tools 43 of 80 Which collaboration features are available in the SAP Community? Note: There are 2 correct answers to this question. ☐ Update Key Deliverable wikis. ☐ Comment on Key Deliverables. ☐ Follow community. ☐ Ask questions. Agile Project Delivery 44 of 80 Which of the following is a key characteristic of the Agile project approach?. ○ Iterative build with frequent inspections. ○ Frequent and detailed release scheduling. ○ Frequent quality gates in each sprint. ○ Higher business involvement in the early phases. Agile Project Delivery 45 of 80 Who determines the tasks that are required to complete the committed backlog items in a Sprint?. ○ Product owner. ○ Project manager. ○ Scrum team. ○ Scrum master. Workstreams Overview 46 of 80 What does the Side-by-Side extensibility option mean?. ○ SAP S/4HANA extensions are context‑aware and focused on tight integration. ○ Extend SAP S/4HANA using APIs published on SAP Business Accelerator Hub. ○ Extending SAP S/4HANA using SAP ABAP Development Workbench. ○ There are two SAP S/4HANA instances: one for standard code and another for custom developments. Transition Path "System Conversion" and "Selective Data Transition" 47 of 80 What is the difference between the System Conversion and New Implementation transition paths to SAP S/4HANA? Note: There are 2 correct answers to this question. ☐ Data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase. ☐ Custom code is developed in System Conversion and adjusted in New Implementation of SAP S/4HANA in the Realize phase. ☐ Custom code is adjusted in System Conversion and developed in New Implementation of SAP S/4HANA in the Realize phase. ☐ Data is migrated in System Conversion and converted in New Implementation of SAP S/4HANA in the Realize phase. SAP Activate Methodology Foundation and Tools 48 of 80 Which of the following tools are considered enablers for digital transformation? Note: There are 3 correct answers to this question. ☐ SAP Signavio Process Navigator. ☐ SAP Activate Community. ☐ SAP Product Availability Matrix. ☐ SAP Roadmap Viewer. ☐ Software Logistics Toolset. Introduction to SAP Activate 49 of 80 Which of the following are levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package? Note: There are 2 correct answers to this question. ☐ Scope Items. ☐ Building Blocks. ☐ Configuration Guides. ☐ Business Process Scenarios. Workstreams Overview 50 of 80 When conducting an upgrade of an SAP S/4HANA Cloud, public edition three system landscape, in which phase are the business roles updated?. ○ Deploy. ○ Explore. ○ Realize. ○ Discover. Agile Project Delivery 51 of 80 How do you set up Scrum teams? Note: There are 2 correct answers to this question. ○ As a cross-functional team covering multiple functions, like configuration, data loads, and testing. ○ Based on end-to-end processes like order-to-cash. ○ Based on group size, but a minimum of 12 people. ○ By type of work, like configuration Scrum, documentation Scrum, and testing Scrum. SAP Activate Methodology Foundation and Tools 52 of 80 In which of the following do you use a work item in Focused Build?. ○ Releases. ○ Sprints. ○ Epics. ○ Waves. Transition Path "Private and Public Cloud" 53 of 80 Which systems are part of the private cloud edition landscape? Note: There are 2 correct answers to this question. ☐ Sandbox. ☐ Evaluation. ☐ Production. ☐ Starter. Agile Project Delivery 54 of 80 What do you do during the sprint retrospective meeting?. ○ Plan future sprints with the customer. ○ Document best practices guided by the Scrum Master. ○ Define sprint activities and best practices with the customer. ○ Discuss best practices with the Scrum Team. Introduction to SAP Activate 55 of 80 What is the most granular level of the methodology you can view in the SAP Roadmap Viewer?. ○ Activities. ○ Deliverable. ○ Workstream. ○ Task. Agile Project Planning 56 of 80 In which phase do you collect the main functional attributes of the product as per the Agile definition?. ○ Discover. ○ Realize. ○ Prepare. ○ Explore. Transition Path "Private and Public Cloud" 57 of 80 Which system tenant is the first to be provisioned when implementing SAP S/4HANA Cloud, public edition?. ○ SAP S/4HANA Cloud Development system. ○ SAP S/4HANA Cloud Sandbox system. ○ Central Business Configuration system. ○ SAP Cloud Identity Services. Transition Path "New Implementation SAP S/4HANA on premise" 58 of 80 In which workshop do you validate SAP standard functionality and collect delta requirements?. ○ Solution design. ○ Fit-to-standard. ○ Solution assessment. ○ Fit-to-gap. Agile Project Planning 59 of 80 What information does the project team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct answers to this question. ☐ Available project resources. ☐ Definition of Done. ☐ Benchmark user story. ☐ Definition of Ready. Workstreams Overview 60 of 80 What is one of the key activities performed towards the end of the Explore phase?. ○ Perform configuration settings in the system. ○ Installation and setup of Sandbox system. ○ Setup of Solution Standardization Board. ○ Operations Planning for operational readiness. Agile Project Planning 61 of 80 Which activity helps the project team identify and add user stories to the backlog?. ○ Assessing documentation requirements. ○ Conducting the fit-to-standard workshop. ○ Benchmarking current business processes. ○ Planning the release and sprints. Agile Project Delivery 62 of 80 According to the Definition of Done, which activity must be completed for each Sprint?. ○ Refinement of user story description must be completed. ○ Configuration must be transported to the production system. ○ Functionality must be released to the business. ○ The solution must be built and configured in the development system. 63 of 80 Which of the following cloud services are available on SAP Business Technology Platform? Note: There are 3 correct answers to this question. ☐ SAP Integration Suite. ☐ SAP Data Migration Cockpit. ☐ SAP Master Data Governance. ☐ SAP Cloud ALM. ☐ SAP HANA Cloud. Transition Path "Private and Public Cloud" 64 of 80 You are implementing SAP S4HANA Cloud, public edition for your customer. How do you activate the pre-configuration?. ○ Via the SAP Business Technology Platform. ○ Via the SAP Contact Center. ○ Via the Central Business Configuration System. ○ Via the SAP Cloud ALM. Agile Project Delivery 65 of 80 What activity do you perform during the daily stand-up meeting?. ○ Demo completed features. ○ Report showstoppers. ○ Re-baseline the release plan. ○ Refine acceptance criteria for the sprint. Workstreams Overview 66 of 80 Which of the following activities take place during the Discover phase in an SAP S/4HANA implementation? Note: There are 2 correct answers to this question. ☐ Create, review, and sign off the Project Management Plan. ☐ Discuss the benefits of SAP Data Warehouse Cloud. ☐ Create, review, and sign off the Project Charter. ☐ Discuss the benefits and functionality of SAP Analytics Cloud. Introduction to SAP Activate 67 of 80 In which phase do you verify the SAP Best Practices content that meets the customer's business needs, and capture delta requirements? Note: There are 2 correct answers to this question. ☐ Discovery. ☐ Prepare. ☐ Realize. ☐ Explore. Transition Path "New Implementation SAP S/4HANA on premise" 68 of 80 When doing a new Implementation on premise or private cloud, which system is recommended to demonstrate standard processes in the Explore phase?. ○ Sandbox. ○ Starter. ○ Trial. ○ Development. Introduction to SAP Activate 69 of 80 Which of the following steps are part of the fit-to-standard process? Note: There are 2 correct answers to this question. ☐ Document integration requirements. ☐ Review Best Practices process flow. ☐ Design-to-be business process models. ☐ Enable customers on standard business processes. Workstreams Overview 70 of 80 In which phase will the customer develop a preliminary strategy for building a target Operations and Support organizational model?. ○ Explore. ○ Discover. ○ Realize. ○ Prepare. Transition Path "New Implementation SAP S/4HANA Cloud, public edition" 71 of 80 Which accelerators support the fit-to-standard workshop in the Explore phase? Note: There are 2 correct answers to this question. ☐ Test plan document. ☐ Quality gate checklist and quality gate guide. ☐ Business-Driven Configuration questionnaire. ☐ Requirements feature in SAP Cloud ALM. Agile Project Planning 72 of 80 What criteria does the Scrum team use to sequence the product backlog? Note: There are 2 correct answers to this question. ☐ Business priority. ☐ Experience of team members. ☐ Technical dependencies. ☐ Length of the sprint. SAP Activate Methodology Foundation and Tools 73 of 80 Which of the following tools can support you in managing requirements and software development for implementation projects? Note: There are 2 correct answers to this question. ☐ SAP Focused Run. ☐ SAP Cloud ALM. ☐ Focused Insights for SAP Solution Manager. ☐ Focused Build for SAP Solution Manager. Transition Path "System Conversion" and "Selective Data Transition" 74 of 80 When performing an SAP Readiness Check in system conversion, what areas are covered within the result? Note: There are 3 correct answers to this question. ☐ Active business functions. ☐ Sizing for SAP S/4HANA. ☐ Recommended SAP Fiori apps. ☐ Complete list of possible simplification items. ☐ SAP and third party interfaces. Transition Path "New Implementation SAP S/4HANA Cloud, public edition" 75 of 80 Which of the following are capabilities of the test automation tool for SAP S/4HANA Cloud, public edition? Note: There are 2 correct answers to this question. ☐ Raises test defect tickets automatically. ☐ Supports recording of SAP GUI-based processes. ☐ Captures test results with screenshots. ☐ Supports the creation of custom test automates. Agile Project Planning 76 of 80 What technique helps a Scrum team to prioritize a large, flat backlog? Note: There are 2 correct answers to this question. ☐ User story mapping. ☐ MoSCoW prioritization. ☐ A/B testing user stories. ☐ Splitting the backlog into epics. Workstreams Overview 77 of 80 You are transitioning to SAP S/4HANA. In which phase do you adjust custom code?. ○ Explore. ○ Realize. ○ Deploy. ○ Prepare. Workstreams Overview 78 of 80 What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?. ○ SAP Roadmap Viewer. ○ SAP Signavio Process Navigator. ○ SAP Cloud ALM. ○ SAP Transformation Navigator. Introduction to SAP Activate 79 of 80 What findings do you document in the Explore Phase Fit‑to‑standard workshops? Note: There are 3 correct answers to this question. ☐ Key user documentation. ☐ Key business decisions. ☐ Process models. ☐ Detailed design of extensions. ☐ Confirmation of scope. Agile Project Planning 80 of 80 What is Scrum of Scrums?. ○ Inspection of code and configuration prior to sprint demo. ○ Alternative to regular Scrum process for a very large team. ○ Integration meeting among the various Scrum teams. ○ Scrum team led by very experienced Scrum master. |