Float time that can be modeled in the scheduling of the routing include: Choose the correct answer(s). A Float before production. B Float after production. C Setup time. D Queue time. E Teardown time.

The duration of an operation consists of a maximum of 5 components. Determine whether this statement is true or false. True. False.

Teardown and wait time are always scheduled simultaneously. Determine whether this statement is true or false. True. False.

Only the minimum wait time is scheduled. Determine whether this statement is true or false. True. False.

Move time is defined only in the operation details. Determine whether this statement is true or false. True. false.

You can only split an operation processing time on a work center with more than 1 individual capacity. Determine whether this statement is true or false. True. false.

Operation can be set to overlap so that the next operation starts before the previous operation has finished. Determine whether this statement is true or false. True. False.

Reduction measures are applied when the lead time schedule of a routing does not fit within the basic date schedule. Determine whether this statement is true or false. True. False.

Which of the following are types of PRT's? Choose the correct answer(s). A Material. B Equipment. C Component. D Miscellaneous. E Document.

PRT is another name for a component that is used in production. Determine whether this statement is true or false. True. False.

The same PRT can be assigned to more than one operation on the same routing. Determine whether this statement is true or false. True. False.