Which of the following is not correct about workstreams? There are 2 correct answers to this question. It is a collection of related deliverables. It is assigned as an attribute to phases, deliverables and tasks. It can span phases. Workstreams are dependent on phase start and end. What are the three elements of SAP Activate? There are 3 correct answers to this question. Tools. SAP Solution Manager. Content. Methodology. Focused Build. Which activities are critical for delivering Agile projects? There are 2 correct answers to this question. Blueprint scheduling. Release planning. Retrospective agenda creation. Sprint planning. In the "New Implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? There are 2 correct answers to this question. DEV. P-system. QAS. Starter system. Which of the following SAP S/4HANA Landscape Transformation options are enabled? There are 3 correct answers to this question. System Consolidation. Migration of Business Units. Migration of Selected Applications. System Upgrade. Security Migration. What is the difference between the "New Implementation of SAP S/4HANA Cloud" and the "New Implementation of SAP S/4HANA" transition paths? There are 2 correct answers to this question. There are different roles in the Application Design and Configuration workstream. SAP S/4HANA uses the Implementation Guide (IMG) and the In-App Extensibility Option for configuration and development and SAP S/4HANA Cloud uses SSCUls and the Side-by-Side Extensibility Option. Different sets of work streams are used for these transition paths. Upgrades of SAP S 4HANA Cloud are managed by SAP,and upgrades of SAP S/4HANA are managed by the customer. Which artifacts are part of the Solution Adoption work stream? There are 3 correct answers to this question. Project Plan. Detailed Design - Business Process. System Go live Announcement (order). Project Business Case. Business Transformation Review (Point of View). How can the project manager help to keep momentum in the project and help to keep the customer involved? There are 2 correct answers to this question. Walk through the solution processes with the stakeholders. Add customer resources to the project to reduce the need for formal training. Leverage agile cycles to build and test the solution. Increase the number of Q-Gates. Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase? There are 3 correct answers to this question. Validation Workshops. Baseline Build. Solution Scope and Value Determination. Design for the Gaps and Deltas. Data Migration Approach. How do you gain access to the SAP Activate Methodology Jam site? Please choose the correct answer. Register on SAP Service Marketplace. Join SAP S/4HANA group on SAP Community Network. Submit e-mail address via on-line form. Send e-mail to SAP contact address. Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase? There are 2 correct answers to this question. Solution Validation Workshop. RICEF Specification Template. Sprint Backlog Template. Quality Gate Checklist. What activities do you perform during the fit-to-standard workshops milestone in the SAP Activate methodology within SAP Cloud ALM?. Create SAP Fiori screen mock-ups in SAP Cloud ALM. Create notes and/or requirements in SAP Cloud ALM. View details of business process diagrams and descriptions in SAP Cloud ALM. View details of high-level process flows in SAP Cloud ALM. Create wireframes for user interfaces in SAP Cloud ALM. What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please choose the correct answer. Start with executable content. Waterfall approach. Limited involvement of business stakeholders. Design-based. Which artifacts in the Testing work stream are created within the Realize phase for the New Implementation of SAP S/4HANA Cloud" transition path? There are 2 correct answers to this question. Functional Test Scenarios. User Acceptance Test – Plan. Functional Specifications. Reporting Functional Specifications. What is the best target deployment option of SAP S/4HANA for the "System Conversion" transition path? Please choose the correct answer. SAP C/4HANA. SAP S/4HANA Cloud. SAP S/4HANA. Hybrid of SAP S/4HANA Cloud and SAP S/4HANA. Arrange the following in the correct sequence of steps followed for a 'Fit to Standard' workshop. Please choose the correct answer. Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Discuss how the process fit with customer requirements, Identify gaps, Identify required configuration, Enable customer on execution of scenarios. Demonstrate Business Scenarios and Concepts, Review Best Practice Process Flow, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps. Discuss how the process fit with customer requirements, Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Enable customer on execution of scenarios, Identify gaps. Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps. What is the order of artifacts within the Technical Architecture and Infrastructure workstream in the Prepare phase? Please choose the correct answer. Technical strategy -> Hardware specification from Hardware Vendor -> Parameters Hardware Sizing calculation -> Hardware Sizing results. Technical Strategy -> Parameters Hardware Sizing calculation -> Hardware Sizing results -> Hardware Specification from Hardware Vendor. Hardware specification from Hardware Vendor -> Technical Strategy -> Parameters Hardware Sizing calculation -> Hardware Sizing results. Hardware specification from Hardware Vendor -> Parameters Hardware Sizing calculation -> Hardware Sizing results -> Technical Strategy. Which of the following are examples of Ready-to-run SAP S/4HANA systems? There are 2 correct answers to this question. SAP Model Company. SAP Best Practices Explorer. SAP Mission ControlCenter. Fully Activated Appliance. Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud' transition path? Please choose the correct answer. Setup and Enablement. Fit-to-standard. Simplification and Custom Code Impact Analysis. Solution Validation and Delta Design. Which deliverable is specific to on-premise and NOT for the cloud? Please choose the correct answer. Knowledge Transfer. Adaptation Specification. Learning Needs Analysis. Technical Design Solution. Which of the following are the pillars of SAP Activate? There are 3 correct answers to this question. Guided Configuration. SAP ASAP Methodology. SAP Launch Methodology. SAP Best Practices. SAP Activate Methodology. When do you perform User Acceptance Testing during the Agile Build? Please choose the correct answer. Before Integration Testing. After Integration Testing. After each Sprint. During each Firm-up Sprint. How would you describe the Realize phase in the "New Implementation of SAP S/4HANA" transition path? Please choose the correct answer. Configure and develop. Configuration copy. Configure. Configure and adjust custom code. Which collaboration features can SAP Activate Jam users access? There are 2 correct answers to this question. Ask questions. Comment on documents. Tweet questions. Update Key Deliverable wikis. Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer. Navigate by assigned Delivery Mode. Navigate by work stream. Navigate by Project Team Member Role. Navigate by RACI matrix accountability. What is the purpose of the Solution Validation activity in the Explore phase? There are 3 correct answers to this question. To challenge changes to standard. To log additional scope items. To identify gaps. To verify technical installation. To educate project participants. What can you do in the SAP Roadmap Viewer tool? Please choose the correct answer. Comment on Deliverables and Tasks within Roadmaps. Download full roadmap content for offline navigation. Navigate detailed Solution Implementation Roadmaps. Create a customer-specific version of a roadmap. Ready-to-use Content in SAP Activate includes which of the following? There are 2 correct answers to this question. Business models from leading companies in each industry sector. SAP Best Practices. Courses delivered by SAP Education. Project Accelerators. What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition? Please choose the correct answer. SAP Best Practices. Rapid prototyping. Full project SCRUM. Project team training. How would you describe the Explore phase in the "New Implementation of SAP S/4HANA Cloud" transition path? Please choose the correct answer. Simplification and Custom Code Impact Analysis. Solution Validation and Delta Design. Fit-to-standard. Setup and Enablement. Which pre-loaded content is available in SAP Cloud ALM for implementation? There are 2 correct answers to this question. Business process best practice content. Activate methodology tasks. Software configurations. Roles and authorizations. In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps? Please choose the correct answer. Realize. Prepare. Deploy. Explore. In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer. Deploy. Realize. Explore. Prepare. How are the build and test tasks planned and executed in the Realize phase? Please choose the correct answer. By using the sprint backlog list as input for each iteration. With Q-Gates for sign off after each iteration. By executing regression tests after each iteration. By using incremental build in fixed-scope iteration. Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new implementations? There are 3 correct answers to this question. Production Support Plan. Change Management Plan. Value Determination. Scope Validation. Value Audits. Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 3 correct answers to this question. Sandbox system migration. Development system migration. Delta configuration. Custom code adjustment. Operations impact analysis. What is the minimum number of Quality Gates mandated for SAP S/4HANA transition projects? Please choose the correct answer. 3. 4. 5. 2. Which of the following activities are part of the Deploy Phase of a Landscape Transformation journey to SAP S/4HANA On-Premise Edition? There are 2 correct answers to this question. Optimize software Change Control Management. Solution Activation. Access organizational and production readiness. Training delivery. Which of the following are part of the 10 SAP Quality Principles? There are 2 correct answers to this question. Plan one phase at a time. Start scoping early. Achieve production readiness. Use standard functionality optionally. What is the purpose of a firm-up sprint? Please choose the correct answer. To revise a release plan and sprint plan. To demonstrate functionality from previous sprint. To perform String test. To run end-to-end integration test. Which tools does SAP Activate provide to support Guided Configuration? There are 3 correct answers to this question. SAP Solution Composer. Self Service Configuration. Model Company. Expert Configuration. Solution Builder. Which artifacts are created within Application Design and Configuration work stream in the Explore phase of the "New Implementation of SAP S/4HANA" transition path? There are 3 correct answers to this question. Organization Structure Specification. Detailed Design - Business Process. Delta Requirements List - Register. Roles and Authorizations Management Concept. Project Procedure - Mock-up Modeling. Who determines the priority of user stories in the backlog of an Agile project? Please choose the correct answer. SCRUM Master. Product Owner. Project Manager. Project Team. Which of the following are not phases of the SAP Activate methodology? There are 2 correct answers to this question. Go-Live & Support. Preparation. Realize. Prepare. Which of the following are levels in the structure of an SAP Best Practices Solution Package? There are 2 correct answers to this question. Business Process Scenarios. Building Blocks. Configuration Guides. Scope Items. How does the provisioning of SAP S/4HANA Cloud differ from the setup of SAP S/4HANA? There are 2 correct answers to this question. To start a Solution Validation workshop, a DEV system is available for SAP S/4HANA, while a Starter system is required for Fit-to-standard for SAP S/4HANA Cloud. In SAP S/4HANA Cloud, decommissioning/shutdown of the Starter system is initiated automatically after the P-system is requested through the Manage Your Solution app, whereas in an SAP S/4HANA system, the DEV system persists. There is a Preset phase for 0-system, which is unique for SAP S/4HANA Cloud. SAP S/4HANA systems take less time to provision than SAP S/4HANA Cloud systems. Where can you find Project Library Accelerators? Please choose the correct answer. SAP Best Practices Explorer. Fully Activated Appliance. SAP Cloud Appliance Library. SAP Roadmap Viewer. Which of the following belong to the Application Design and Configuration work stream for SAP S/4HANA Cloud in the Explore phase? There are 2 correct answers to this question. Integration prerequisites confirmation. Fit-to-standard workshop. Kick-off workshop. Configuration definition. What capabilities does SAP API Business Hub pro ide to help you select integration options for your project? There are 3 correct answers to this question. Integration with Ide and code generation. Advice on selecting scope items in SAP Best Practices Explorer. Sandbox for testing APls. Recommendations on using integration bus (SAP Process Orchestration or SAP Integration Suite). Pre-packaged integrations. What do you do during post cutover? Please choose the correct answer. Setup Operational Support. Conduct Organizational Readiness Check. Perform the Verification Session of the SAP Going Live Check. Perform Technical System Test. Which of the following statements about Scrum is correct? Please choose the correct answer. In Scrum, the team is Self-organized, define all task necessary for all project life cycle. In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies. The three ceremonies are sprint planning, daily scrum, sprint review (retrospective). Scrum Master defines and prioritizes features and gathers requirements. Which of the following tasks are part of the Production support after the Go Live key deliverable? There are 2 correct answers to this question. Perform a Technical systems test. Provide further training to customer end users. Resolve issues identified during the Hyper Care period. Set up the Operations Control Center. In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project? Please choose the correct answer. Explore. Realize. Deploy. Prepare. In which phase should you create a Data Migration Strategy (LO) during a Selective Data Transition? Please choose the correct answer. Realize. Explore. Deploy. Discover. Which component of SAP Activate offers customers a reference solution in the cloud for a quick start? Please choose the correct answer. Guided Configuration. SAP Best Practices. SAP Implementation Assistant. SAP Activate Methodology. Which of the following is a key characteristic of the Agile project approach? Please choose the correct answer. Frequent quality gates. Iterative build with frequent inspections. Formal and detailed documentation. Frequent and detailed project scheduling. What is a benefit of using Guided Configuration instead of the Implementation Guide? Please choose the correct answer. It ensures SAP updates do NOT conflict with customer configurations. It eliminates the need to generate transport requests for configuration settings. It ensures configuration is done using SAP Solution Manager. It eliminates the need for Content Lifecycle Management. The hyper care period is part of which phase? Please choose the correct answer. Realize. Explore. Go-Live. Deploy. Which content is made available after you activate SAP Best Practices for a new financial implementation? There are 2 correct answers to this question. Online help. Pre-configured business processes. Implementation Guide. Standard chart of accounts. What term is used for a Ready-to-run SAP S/4HANA system with pre-built Solution Documentation, which supports End-to-End Processes for a specific industry so that the Project Team can focus on differentiation and innovation? Please choose the correct answer. SAP Cloud Appliance Library. SAP Model Company. Best Practice System. Fully Activated Appliance. In which phase do you create a prioritized list of user requirements? Please choose the correct answer. Explore. Realize. Deploy. Prepare. Which of the following are key aspects of business process monitoring? There are 3 correct answers to this question. Process change analysis. Automated problem resolution. Predefined KPIs with process content. Process mining reports. Root cause analysis. What are the responsibilities of the Project Team on level 4 in the picture below? There are 2 correct answers to this question. Set Project policy, standards and oversight. Perform status reporting and communication. Set business priorities, goals and objectives. Identify and resolve issues and risks. What is a difference between the SAP Activate methodology for a new implementation of SAP S/4HANA cloud edition and a new implementation of SAP S/4HANA on-premise? Please choose the correct answer. For the cloud edition, there is an additional work stream for integration with on-premise systems. For on-premise, there are additional deliverables for the system setup. For the cloud edition, there is an additional Q-Gate for integration with on-premise systems. For on-premise, there is an additional Q-Gate for system installation. Which of the following activities support the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 2 correct answers to this question. Non-production systems migration. Custom code Adjustment planning. Data aging configuration. Value determination. In the System conversion to SAP S/4 HANA Deploy phase, which of the following tasks are included? Please choose the correct answer. Final testing. Hyper care support. Scheduling project plan. Interface setup. In which phase do you execute the User Acceptance Test? Please choose the correct answer. Build and Test. Deploy. Realize. Final Preparation. What is the hierarchy level under Phase in the SAP Jam space for SAP Activate on-premise? Please choose the correct answer. Work Stream. Key Deliverable. Scenario. Task. What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the "System Conversion" transition path? Please choose the correct answer. Software Provisioning Manager. SAP Code Inspector. Simplification Item Check (SI-Check). Software Update Manager with Database Migration Option. What is the key characteristic of Agile project delivery? Please choose the correct answer. Iterative build with frequent inspections. Formal and detailed documentation. Frequent Quality Gates. Frequent and detailed project scheduling. What does SAP Activate recommend to keep team members informed and aligned? Please choose the correct answer. Daily progress review meeting with sponsor. Daily e-mail status updates to project manager. Daily team stand-up meeting. Daily status meeting with project manager. What are the core capabilities in SAP Cloud ALM for implementation? There are 3 correct answers to this question. Custom code management. Test management. Task management. Process management. Portfolio management. Where can you find Data Migration templates? Please choose the correct answer. SAP Cloud Appliance Library. SAP Roadmap Viewer. SAP S/4HANA Migration Cockpit. SAP Best Practices Explorer. How many deliverables are a part of the Key Deliverable 'Project Initiation'? Please choose the correct answer. Two. One. Three. Four. Identify the two landscape transformation specific tasks in the explore phase. There are 2 correct answers to this question. Setup Landscape Transformation Software. Run a Landscape Transformation Assessment. Perform Client transfer. Define the Data Migration Architecture. Who determines the tasks that are required to complete the committed backlog items in a sprint? Please choose the correct answer. Project Team. Product Owner. SCRUM Master. Project Manager. In which of the following project phases is it important to plan and schedule data loads followed by load validation activities? Please choose the correct answer. Explore. Prepare. Deploy. Realize. In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the correct answer. Includes Fit/Gap analysis instead of Blueprint. Supports only new implementations. Supports cloud deployments. Leverages iterative incremental build. What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices? Please choose the correct answer. Activate and apply SAP Best Practices with SAP Solution Manager. Activate and apply SAP Best Practices content with the self-service configuration UI. Assemble and apply SAP Best Practices to the system. Apply SAP Best Practices with the Configure your Solution application. What are the three pillars of SAP Activate? There are 3 correct answers to this question. Guided Configuration. SAP Solution Manager. SAP Best Practices. SAP S/4HANA in-memory database. SAP Activate Methodology. |