Which of the following is true about a cloud implementation project?. The entire transport system is kept intact and up and running. The Starter system is specific to SAP S/4 HANA cloud. Starter systems are not required to be in place for the 'Fit to Standard' workshops. In the prepare phase of a cloud implementation project the project team provides the customer with materials to review self enablement.

Which of the following activities are part of the Deploy phase of a Landscape Transformation journey to SAP S/4 HANA On-Premise Edition?. Optimize software change control Management. Training Delivery. Solution Activation. Access organizational and production readiness.

What do you do during an iterative approach to build a solution?. Build the solution module by module. Provide a working solution only at the end of the release. Include frequent inspection check-points. Deliver a prototype of the solution.

In which phase of the SAP Activate methodology does the team complete the transformation planning?. Realize. Deploy. Explore. Prepare.

In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project?. Deploy. Explore. Prepare. Realize.

Which of the following tasks are required in the Prepare Phase?. Set up the infrastructure to support the project. Approve the test strategy. Define the communication plan. Identify relevant SAP Best practices. Train the Project team.

Which of the following is a Key Deliverable of the prepare phase?. Release and Sprint Plan. Baseline build. Solution Scope and Value Determination. Change Impact Analysis and Communication Plan.

Which of the following is not correct about Fit/Gap Analysis?. Validate pre-activate and pre-assembled solution in the development system. Minimize the needs for rework during realization. Prioritize delta requirement and gaps. Drive towards adopting customers process.

What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices?. Assemble and apply SAP Best Practices to the system. Apply SAP Best Practices with Configure your solution application. Activate and apply SAP Best Practices content with the self-service Configuration UI. Activate and apply SAP Best Practices with SAP Solution Manager.

Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase. Validation Workshops. Design for the Gaps and Deltas. Solution Scope and Value Determination. Baseline Build. Data Migration Approach.

Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new implementations?. Change Management Plan. Value Audits. Production Support Plan. Scope Validation. Value Determination.

Which key activities does the Guided Configuration support you with?. Create test data. Manage roles of configuration users. Train new users. Test configured processes. View solution scope.

Which key deliverable includes the development of RICEFW objects?. Custom Extension Management. Development Build. Enhancement Delivery. Sprint Execution.

How can SCRUM teams be organized?. By work stream. By job title. By Project governance level. By project phase.

Which of the following can be used to navigate through the roadmap?. Deliverables. Workstreams. Phases. Tasks.

What is difference between the SAP Activate methodology for a new implementation of SAP S/4 HANA cloud edition and a new implementation of SAP S/4 HANA on-Premise?. For the cloud edition, there is an additional Q-Gate for integration with on-Premise systems. For on-premise, there is a additional Q-Gate for system installation. For on-premise, there are additional deliverables for the system setup. For the colud edition, there is an additional work for integration with on-premise systems.

Which accelerator can help you document the detailed design of solution extensions?. RICEF Specification template. Change Request Template. Sprint Backlog Template. Product Backlog Template.

Which content packages are available in the SAP Package Library?. Rapid Deployment Solutions. SAP Best Practices. Solution Builder. SAP Activate Methodology.

Which of the following is not correct about the REALIZE phase?. The beginning of the Realize phase the team prepares a list of all the requirements in a backlog. The team prepares for operations so that the functionality can be brought live. Detailed design workshops are held. The project team ensures that the build is meeting the business requirements.

Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4 HANA implementation?. Adjusting custom code objects. Implementing best practices. Creating transactional data. Channing master data. Organizational Structure.

What are deliverables of the "Application Design and Configuration" work stream in the prepare phase?. Data Cleansing. Fit/Gap Analysis. Adaption Specificatoins. Security Checks. Network Connectivity Checks.

Which tools does SAP Activate provide to support Guided Configuration?. Expert Configuration. Self Service Configuration. SAP Solution Composer. Model Company. Solution Builder.

How are the build and test tasks planned and executed in the Realize phase?. By using incremental build in fixed-scope iteration. By executing regression tests after each iteration. With Q-Gates for sign off after iteration. By using the sprint backlog list as input for each iteration.

In which phase does the Transition to Operations workstream start ?. Deploy. Realize. Prepare. Explore.

In which phase of the SAP Activate methodology does the team complete the System Assessment?. Deploy. Prepare. Explore. Realize.

Which of the following activities support the Realize Phase of a System Conversion Journey to SAP S/4 HANA On-Premise edition?. Non-Production system migration. Data again configuration. Custom code adjustment planning. Value determination.

What do you do during post cutover?. Conduct Organizational Readiness Check. Perform the verification session of the SAP going live check. Setup Operational support. Perform Technical system test.

What are the responsibility of the Team Lead on Level 4?. Setup Project policy, standards and oversight. Identify and resolve issues and risks. Perform status reporting and communication. Set Business priorities , goals and Objectives.

Which of the following are available in the initial SAP Methodology JAM page?. Task description. Roadmaps. Summary. Accelerators.

In the System conversion to SAP S/4 HANA deploy phase , which of the following tasks are included?. Scheduling project plan. Final Testing. Interface setup. Hyper care support.

Which of the following statements about SCRUM is correct?. The three ceremonies are sprint planning, daily scrum, sprint review(retrospective). In Scrum, as best practices , we have three main roles and three artifacts or three ceremonies. In Scrum, the team is self organized, define all task necessary for project life cycle. Scrum master defines and prioritizes features and gathers requirements.

Which of the following is NOT a characteristic that the quality principles are based on?. International Standard. Best Practices. Experienced of Typical Pitfals. SAP Quality Award example winners.

What can users do in Roadmap viewer tool?. Display and navigate detailed SAP Activate methodology WBS. Download full SAP Activate methodology content for use off-line. Create a customer specific version of SAP Activate methodology. Upload SAP Activate WBS into SAP Solution Manager 7.1.

How can the project manager help to keep the momentum in the Project and help to keep customers involved?. Increase number of Q-gates. Leverage agile cycles and build and test the solution. Walk through the solution process with the stakeholders. Add customer resources to the project to reduce the need for formal training.

What is SAP Activate. A bundle of ASAP, SAP Launch and Rapid deployment solution. A combination of best practices , methodology and guided configuration. A step-by-step instruction on how to remove from the SAP best practices to your custom solution. A methodology for each of the deployment modes(cloud, on-premise, hybrid).