Which of the following statement are the true regarding the SAP JAM site? Choose the correct answer. only one correct It provides information only on cloud deployments. It provides information on both premise and cloud deployments. It provides information only on premise deployments.
Which deliverable is specific to on-premise and NOT for the cloud? Please choose the correct answer. Adaptation Specification Technical Design Solution Learning Needs Analysis Knowledge Transfer.
In SAP Activate, what replaces the detailed Blueprint from ASAP? Please choose the correct answer. Business Process Mapping Value Determination Custom Extension management Fit/Gap Workshops.
How can the project manager help to keep momentum in the project and help to keep the customer involved? There are 2 correct answers to this question. Walk through the solution processes with the stakeholders Leverage agile cycles to build and test the solution Add customer resources to the project to reduce the need for formal training Increase the number of Q-Gates.
Which of the following tasks are required in the Prepare Phase? There are 3 correct answers to this question. Train the project team Define the communication plan Approve the test strategy Set up the infrastructure to support the project Identify relevant SAP Best Practices.
What is the objective of a sprint retrospective meeting? Please choose the correct answer. Define the stakeholder management approach Provide formal feedback to the project manager Review and prioritize the backlog Improve the SCRUM process.
Which activities are critical for delivering Agile projects? There are 2 correct answers to this question. Retrospective agenda creation Sprint planning Release planning Blueprint scheduling.
Which component of SAP Activate offers customers a reference solution in the cloud for a quick start? Please choose the correct answer. SAP Best Practices Guided Configuration SAP Implementation Assistant SAP Activate Methodology.
Which of the following activities support the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 2 correct answers to this question. Data aging configuration Value determination Custom code Adjustment planning Non-production systems migration.
What is the purpose of the scrumboard? Please choose the correct answer. To show the functional breakdown of the solution scope To document the results of integration testing To manage the resource load To visualize team progress.
How many deliverables are a part of the Key Deliverable 'Project Initiation'? Please choose the correct answer. Four Three Two One.
Arrange the following in the correct sequence of steps followed for a 'Fit to Standard' workshop. Please choose the correct answer. Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Discuss how the process fit with customer requirements, Identify gaps, Identify required configuration, Enable customer on execution of scenarios Discuss how the process fit with customer requirements, Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Enable customer on execution of scenarios, Identify gaps Demonstrate Business Scenarios and Concepts, Review Best Practice Process Flow, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps.
Which of the following is not correct about Fit/Gap Analysis? There are 2 correct answers to this question. Drive towards adopting customers processes. Minimize the needs for rework during realization. Prioritize delta requirement and gaps. Validate pre-activate and pre-assembled solution in the development system.
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the correct answer. Prepare Realize Deploy Explore.
Which key deliverable includes the development of RICEFW objects? Please choose the correct answer. Development Build Custom Extensions Management Sprint Execution Enhancement Delivery.
What is the purpose of the Solution Validation activity in the Explore phase? There are 3 correct answers to this question. To educate project participants To verify technical installation To identify gaps To log additional scope items To challenge changes to standard.
What do you do during Sprint Execution? Please choose the correct answer. End a sprint when the sprint backlog items are all complete Hold a retrospective at the end of each week Present status of selected user stories in the sprint scope on a scrumboard Measure the sprint progress with a percentage complete report.
When do you perform User Acceptance Testing during the Agile Build? Please choose the correct answer. During each Firm-up Sprint After Integration Testing Before Integration Testing After each Sprint.
What is the purpose of the Solution Builder tool in the SAP Activate Guided Configuration? Please choose the correct answer. To activate the Best Practices content To personalize activated, ready-to run business processes To create delta building blocks for complementary content To create customer-specific scope items.
Which new project roles are introduced with the SAP Activate Agile methodology? There are 2 correct answers to this question. Integration Lead Product Owner Design Thinking Coach SCRUM Master.
In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the correct answer. Supports only new implementations Includes Fit/Gap analysis instead of Blueprint Supports cloud deployments Leverages iterative incremental build.
What is SAP Activate? Please choose the correct answer. A methodology for each of the deployment modes (cloud , on-premise, hybrid) A step-by-step instruction on how to remove from SAP best practices to your custom solution A combination of SAP best practices , methodology, and guided configuration A bundle of ASAP , SAP Launch , and Rapid Deployment Solutions.
What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question. Fixed scope Start with SAP Best Practices On-premise only Premium engagement ready Validate solution.
Which of the following dimensions need to be considered during prioritization? Choose all corrects Integration Importance Scaling.
Which of the following is true about a cloud implementation project? There are 2 correct answers to this question. The entire transport system is kept intact and up and running. The Starter System is specific to SAP S/4HANA Cloud. Starter Systems are not required to be in place for the 'Fit to Standard' workshops. In the prepare phase of a cloud implementation project the project team provide the customer with materials to review as self-enablement.
What information does the product team need so that they can estimate the relative size of backlog user story correctly? Please choose the correct answer. Available project resources Definition of Done Overall project schedule Test strategy.
Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation? There are 3 correct answers to this question. Implementing best practices Creating transactional data Organizational structure Adjusting custom code objects Changing master data.
What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition? Please choose the correct answer. SAP Best Practices Full project SCRUM Rapid prototyping Project team training.
What is the focus of a SCRUM of SCRUMS in an Agile context? Please choose the correct answer. Communication to the Project Management Office Backlog management Integration topics Best Practice adoption.
Which of the following are the benefits of SAP JAM? There are 2 correct answers to this question. User collaboration Highly available Reduced Recovery Time Easy to use.
Which of the following SAP S/4HANA Landscape Transformation options are enabled? There are 3 correct answers to this question. Security Migration Migration of Business Units System Upgrade System Consolidation Migration of Selected Applications.
In which of the following project phases is it important to plan and schedule data loads followed by load validation activities? Please choose the correct answer. Prepare Explore Realize Deploy.
Which of the following are the pillars of SAP Activate? There are 3 correct answers to this question. SAP Best Practices SAP ASAP Methodology SAP Activate Methodology Guided Configuration SAP Launch Methodology.
What is a difference between the SAP Activate methodology for a new implementation of SAP S/4HANA cloud edition and a new implementation of SAP S/4HANA on-premise? Please choose the correct answer. For the cloud edition, there is an additional work stream for integration with on-premise systems For on-premise, there are additional deliverables for the system setup For on-premise, there is an additional Q-Gate for system installation For the cloud edition, there is an additional Q-Gate for integration with on-premise systems.
Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 correct answers to this question. Conduct Scope Validation Schedule kick-off workshop Perform Fit/Gap Analysis Confirm Integration prerequisites.
Which of the following tasks are part of the Production support after the Go Live key deliverable? There are 2 correct answers to this question. Resolve issues identified during the Hyper Care period Set up the Operations Control Center Provide further training to customer end users Perform a Technical systems test.
What is the most granular level of the methodology you can view in the Roadmap Viewer? Please choose the correct answer. Task Phase Deliverables Scenario.
How are the build and test tasks planned and executed in the Realize phase? Please choose the correct answer. By using the sprint backlog list as input for each iteration By using incremental build in fixed-scope iteration With Q-Gates for sign off after each iteration By executing regression tests after each iteration.
What is the correct order of the SAP Activate Methodology phases? Plan -> Build -> Run -> Sustain Discover -> Prepare -> Explore -> Realize -> Deploy -> Run Plan -> Design -> Build -> Operat Prepare -> Discover -> Explore -> Realize -> Deploy -> Run.
What are the three elements of SAP Activate? Note: There are 3 correct answers to this question. Content Methodology Focused Build Tools SAP Solution Manager.
Where can you find Project Library Accelerators? Fully Activated Appliance SAP Roadmap Viewer SAP Cloud Appliance Library SAP Best Practices Explorer.
What can you do in the SAP Roadmap Viewer tool? Comment on Deliverables and Tasks within Roadmaps. Download full roadmap content for offline navigation. Create a customer-specific version of a roadmap. Navigate detailed Solution Implementation Roadmaps.