Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? There are 2 correct answers to this question. In-house production time. Total replenishment lead time. Planned delivery time. Operation duration. Under what circumstances can you change the material type if stocks, reservations, or purchasing documents exist? There are 2 correct answers to this question. The same batch management level is used. The quantity and values updates are the same. The same account category is used. The same base unit of measurement is used. What does the industry sector determine? There are 2 correct answers to this question. Whether a material master field is required, changeable, displayed, or hidden. Which transaction you can use to create a new material. Which material master views can be maintained. Whether material numbers are assigned internally or externally. SAP supports digital transformation of organizations and making enterprises intelligent. What are the components of an intelligent enterprise? There are 3 correct answers to this question. SAP Business Technology Platform. Intelligent Technologies. Intelligent Suite. SAP Activate Methodology. SAP Best Practices. Which time elements are relevant for lead time scheduling of a production order? There are 2 correct answers to this question. Planned delivery time. Setup time. Total replenishment lead time. Float after production. For an in-house scenario, what are characteristics of MRP in classic ERP? There are 2 correct answers to this question. It generates released production orders. It uses demand elements as input. It generates a feasible solution as output. It uses infinite planning. Your customer wants to include restricted-use stock as a potential receipt in the existing ATP check for component availability. Which information is required to implement this change request in the scope of check? There are 2 correct answers to this question. The checking rule from the business application. The checking group from the material master. The checking control for the order type. The ATP category for restricted-use stock. What information is included in the SAP Readiness Check result for SAP S/4HANA? There are 3 correct answers to this question. Inconsistent data tables. Recommended SAP Best Practices. Relevant simplification items. Custom code analysis. Recommended SAP Fiori apps. Your client uses process orders for the production of liquid chemicals. What can you define to ensure that the flow happens only in physically connected tanks?. Resource network. Operation network. Setup matrix. Work center hierarchy. What kind of demands form a demand program? There are 3 correct answers to this question. Customer requirements. Stock requirements. Stock transfer requirements. Forecast requirements. An operation isn't transferred to the PP-DS component in PDS. What are the possible reasons? There are 2 correct answers to this question. Response. The control key for the operation isn't relevant for detailed capacity requirement and scheduling. The work center assigned in the operation isn't relevant for advanced planning. The setup time isn't maintained in the operation. A BOM component assigned to the operation isn't available in PP-DS. You want to use capacity availability checks for production orders. Which settings have to be made for this? There are 2 correct answers to this question. Response: An overall profile must be assigned in the checking control. The Relevant for Finite Scheduling indicator must be set. A checking rule must be assigned in the checking control. The PRT Availability Check must be set in the checking control. In net requirements planning of the MRP, which of the following are seen as requirements? There are 2 correct answers to this question. Fixed receipts. Stock. Sales orders. Safety stock. The production plan is being disrupted by last minute demands that are entered in the system. Which is the most efficient way to handle last minute demands and protect the current production plan? There are 2 correct answers to this question. In the material master record, set MRP type to P4 and a planning time fence on the replenishment lead time of the material. In the stock requirements list, set a manual firming fence for a date based on the replenishment lead time of the material. In the material master record, set MRP type to P1 and a planning time fence on the replenishment lead time of the material. Manually firm all planned orders for materials within the replenishment lead time of the material. To execute the subcontracting process in PP-DS, what must be set up in SAP S/4HANA? There are 2 correct answers to this question. Routings. Storage locations as MRP areas. Product versions. Subcontracting MRP areas. What statements are true concerning a plant? There are 3 correct answers to this question. Product costing can be performed across plants. A plant/division combination can be assigned to only one business area. A plant can belong to many company codes. Several purchasing organizations can be assigned to a plant. What does the material type influence? There are 2 correct answers to this question. Which document types are allowed. Which plant specific status is allowed. Whether the material is produced in-house, procured externally or both. Which material master views can be maintained. Which master data can’t be transferred to PP-DS if the CIF models aren’t generated and activated? Please choose the correct answer. Response: Production data structures. Purchasing info records. Work centers. Materials. What can you use heuristics in Advanced planning (PP/DS) for? Please choose the correct answer. To automate material movements in material staging. To set default values in production master data. To optimize costs and times in production plants. To solve planning problems for defined objects. Which view contains the user-defined class assignments for a material? Please choose the correct answer. Materials planning view. Classification view. Basic data view. Your client uses process orders for the production of liquid chemicals. What can you define to ensure that the flow happens only in physically connected tanks? Please choose the correct answer. Setup matrix. Work center hierarchy. Resource network. Operation network. What are the possible categories for the Business Partner master data object in SAP S/4HANA? There are 3 correct answers to this question. Group. Person. Vendor. Organization. Customer. The BOM is exploded during backflushing based on which of the following? There are 2 correct answers to this question. If a revision level and a planned order are maintained, then the revision level has the higher priority. If a planned order is maintained, then the component list of the planned order is exploded. The system will always explode the BOM based on the creation date of the BOM. The system explodes the current BOM (from the production version) based on the posting date. What are key benefits of SAP S/4HANA MRP Live? There are 2 correct answers to this question. Significantly higher data footprint leveraging SAP HANA. Runs on any device. Simultaneous capacity planning by default. Real-time analysis of disruptions in the material flow. The production order default storage location for components can be defined in which of the following master data objects? There are 2 correct answers to this question. Response: BOM item details. Material master of components. Routing, in the component allocation. Location field maintained in the work center. With reference to confirmations, which statements are correct? There are 3 correct answers to this question. Response: The standard value key maintained in the work center determines whether an operation is relevant for confirmation or not. For progressive confirmation, you can perform confirmation at the end of the day. By default, you can perform only partial confirmation while performing milestone confirmation. With milestone confirmation, the preceding operations and suboperations will be confirmed until the next milestone operation. Capacity requirements will be completely reduced when you perform final confirmation. Question: Which of the following belong to supply chain master data objects? There are 2 correct answers to this question. Account. Vendor. Distribution center. Product cost collector. Which of the following statements are true for make-to-order production? There are 2 correct answers to this question. Sales orders are fulfilled by anonymous warehouse stock. Sales orders always trigger production. Planned independent requirements always trigger final assembly. Planning assemblies can be combined with the Make-to-Order concept. In the Schedule Production app, which settings can you make in the planning strategy? There are 3 correct answers to this question. Direction (forward/backward). Scheduling control (finite/infinite). Fixed pegging (on/off). Planning mode (bucket/sequence). Finiteness level (0...1). What does forecasting in the demand planning cycle include? There are 3 correct answers to this question. Response: Past quotation quantities. Market intelligence. Past sales order quantities. One-off events. Past procurement quantities. Which material master view is mandatory to enable discrete manufacturing? Please choose the correct answer. Work Scheduling view. Advanced Planning view. Accounting 1 view. MRP 4 view. What does the PP/DS optimization optimize? Please choose the correct answer. It minimizes the number of possible solutions. It minimizes an objective function. It maximizes the ROI. It minimizes the resource utilization. How can you set up the supply source for the SAP Kanban process? There are 3 correct answers to this question. Using quotations for internal and external procurement. Using purchase orders for external procurement. Using stock transfer reservations for stock transfer. Using purchasing costs for automated source prioritization. Using run schedule quantities for in-house production. Which are the possible restrictions of MRP Live? There are 2 correct answers too this question. Configurable materials aren't supported in MRP Live on SAP HANA. Production version only considers the first BOM alternatives for planning in MRP Live on SAP HANA. Using the Advanced planning flag enables select materials in embedded PPDS to be treated separately in MRP Live on SAP HANA. Time-phased planning isn't yet supported in MRP Live on SAP HANA. What is the purpose of collective orders? Please choose the correct answer. To post production costs on a cost collector instead of the production order. To post any component withdrawals single back flush with order confirmation. To manage production orders for an entire finished production multiple levels. To combine order management of co-products and by-products with the main product. Which advanced functionality has been embedded in SAP S/4HANA? There are 3 correct answers to this question. Backorder processing. Available-to-promise. Supply Network Planning. Demand planning. Capacity planning. Which of the following statements are true for make-to-stock production? There are 3 correct answers to this question. Sales orders always trigger production. Planning assemblies can be combined with the make-to-stock concept. Planned independent requirements always trigger assembly. Sales orders are fulfilled by anonymous warehouse stock. Capacity Planning: In which of the following ways can you model downtimes of work center capacities? There are 2 correct answers to this question. Defining time periods that are not plannable in the planning table. Defining non-working periods in factory calendars. Creating alternative resources to relieve the non-working capacity. Defining special downtime work centers without activity types. Which of the following is correct for reference operation sets? There are 3 correct answers to this question. You can assign PRTs to a reference operation set. Operations that are standard for several task lists/routings can be defined as reference operation sets. Reference operation sets allow only the standard sequence. Parallel and alternative sequences are allowed for a reference operation set. You can assign PRTs to a reference operation set. Which chart types does the tabular planning table provide in SAP S/4HANA? There are 2 correct answers to this question. Order (pool) chart. Work center capacities chart. Orders (dispatched) chart. Capacity requirements chart. What does the Material Requirements Planning run trigger? There are 2 correct answers to this question. The creation of planned orders. The creation of production orders. The creation of planned independent requirements. The creation of planned requirements. Which statements are correct with reference to capacity leveling? There are 3 correct answers to this question. Response: The drag and drop method can be used for dispatching in graphical planning. Both tabular and graphic planning tables are part of future architecture of SAP S/4HANA. Dispatch of operations is the main function of capacity leveling. One work center can't be occupied by several operations at the same time. The tabular capacity planning table provides period-oriented aggregated information for the available capacities. What is the sequence of the five steps of Demand-Driven Replenishment in SAP S/4HANA? Please choose the correct answer. Analytics, buffer positioning, replenishment planning, buffer sizing, replenishment execution. Analytics, buffer positioning, replenishment planning, replenishment execution, buffer sizing. Analytics, buffer positioning, buffer sizing, replenishment planning, replenishment execution. Analytics, replenishment planning, replenishment execution, buffer positioning, buffer sizing. Where can you find the latest in version of the Simplification List for SAP S/4HANA? Please choose the correct answer. SAP Best Practices Explorer. SAP Support Portal. SAP Help Portal. SAP Solution Manager 7.2. Which of the following deployment option provides the latest innovations delivered quarterly? Please choose the correct answer. SAP S/4HANA, hybrid edition. SAP S/4HANA AnyPremise edition. SAP S/4HANA Cloud, extended edition. SAP S/4HANA Cloud, essentials edition. For which categories can you define bills of materials (BOMs) in SAP S/4HANA? There are 2 correct answers to this question. Document Structure. Work Center. Sales Order. Class. What are examples of assignment objects you can maintain in the Engineering Workbench? 3an. Material to bill of materials (BOM) assignment. Component assignment. Material to routing assignment. Routing to sequence assignment. Material to production version assignment. |