1. In the context of the capacity scheduling table, how do you define a pacemaker work centre?. A. By assigning it to the first operation of a routing. B. By assigning it to the production version. C. By assigning it to the bottleneck operation. D. By assigning it to the capacity scheduling table. 2. Which planning strategies can you use in the capacity scheduling table? Note: There are 2 correct answers to this question. A. Scheduling control > Find slot. B. Planning mode > Bucket. C. Scheduling control > Close gap. D. Planning mode > Order priority. 3. Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question. A. Setup time. B. Total replenishment lead time. C. Opening period. D. Float after production. 4. What is a work centre hierarchy?. A. A group of alternative work centres providing a cumulative available capacity for production. B. A group of work centres in a parallel sequence that is used to split production quantities and work on them in parallel. C. A group of work centres in a production line that is used in sequence for production. D. A group of alternative work centres for production, structured in hierarchy levels by priorities. 5. Which operations are considered in the capacity scheduling table? Note: There are 2 correct answers to this question. A. Only bottleneck operations. B. Sub-operations. C. Operations assigned to a pacemaker work centre. D. All operations. 6. Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question. A. Order (pool) chart. B. Capacity requirements chart. C. Work centre capacities chart. D. Order (dispatched) chart. 7. In the bucket planning mode of the capacity scheduling table, what happens if the sum of the requirements of all operations exceeds the available capacity of the bucket?. A. The operation CANNOT be dispatched. B. The operation is rescheduled in the planning direction. C. The operation is rescheduled backwards. D. The operation is rescheduled to an alternative work centre. 8. How are dependent requirements for assemblies created? Note: There are 2 correct answers to this question. A. They are created on the assembly level during the planning run. B. They are only created for multilevel bill of material (BOM) structures. C. They are created with exact times in Advanced Planning. D. They are created together with the independent requirement for the finished product. 9. You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of a material shortage. What must you do? Note: There are 2 correct answers to this question. A. Add the agreement to the source list and mark it for MRP relevance. B. Set the creation indicator for purchase requisitions on the initial screen of the MRP run. C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run. D. Add the agreement to the quota arrangement and mark it for MRP relevance. 10. Which options do you have to exclude Advanced Planning materials from the standard MRP run in SAP S/4HANA? Note: There are 2 correct answers to this question. A. Use a different MRP planner for PP/DS materials. B. Use the special MRP type XO. C. Use the material number for selection. D. Use a propagation range. 11. Which time elements does MRP consider in backward scheduling to determine the basic dates for components from dependent requirements? Note: There are 2 correct answers to this question. A. Total replenishment lead time. B. Planned delivery time. C. Operation duration. D. In-house production time. 12. Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question. A. MRP group. B. Material type. C. MRP type. D. Procurement type. 13. Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question. A. ATP quantities. B. Planned orders (unfirmed). C. Production orders. D. Planned orders (firmed). 14. In SAP documentation for MRP in Advanced Planning, you read that the MRP creates new planned orders through infinite scheduling. What does this mean for the capacity requirements of the new planned order?. A. MRP creates the capacity requirements on resources at the earliest possible production time. B. MRP automatically assigns the capacity requirements after the last scheduled operation for each resource. C. MRP automatically assigns the capacity requirements to resources with the earliest available capacity. D. MRP creates the capacity requirements without considering existing load on the resources. 15. Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?. A. Make-to-stock production (10). B. Assembly processing with production orders (82). C. Planning with final assembly (40). D. Planning without final assembly (50). 16. Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question. A. Sales orders have to be ATP-confirmed (available-to-promise) to be saved. B. Net requirements calculation is carried out for every sales order individually. C. Production and procurement costs are managed on the sales order item level. D. Storage location MRP areas are required to manage sales-order-specific stock. E. Planned orders are created in MRP with reference to sales orders. 17. You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semi-finished material?. A. Assembly processing with production orders (82). B. Production by lot size (30). C. Planning with final assembly (40). D. Planning at assembly level (70). 18. You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?. A. Choose planning strategy 20 (Make-to-Order) and select the corresponding Mixed MRP indicator. B. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Individual/Collective indicator. C. Choose planning strategy 20 (Make-to-Order) and select the corresponding Individual/Collective indicator. D. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Mixed MRP indicator. 19. What are some advantages of using Kanban for material supply? Note: There are 2 correct answers to this question. A. Replenishment is always triggered on a regular basis. B. Material is only kept available in small quantities in production. C. Replenishment is only triggered when components are required. D. Material stock is built up for a long period of time in production. 20. What is the focus of repetitive manufacturing?. A. Production of lot size one. B. Period and quantity-oriented production. C. Detailed tracking of production orders. D. Low volume production. 21. How do you model a production line in repetitive manufacturing?. A. As an operation. B. As a work centre. C. As a resource network. D. As a routing. 22. Which order type is used for repetitive manufacturing?. A. Process order. B. Kanban order. C. Production order. D. Planned order. 23. Which of the following are replenishment strategies for Kanban containers? Note: There are 2 correct answers to this question. A. Replenishment using planned independent requirements. B. Replenishment using direct transfer posting. C. Replenishment using reservations. D. Replenishment using process orders. 24. When does the system trigger replenishment for a Kanban container?. A. When you set the container to Waiting. B. When you set the container to Empty. C. When you set the container to Full. D. When you set the container to In transit. 25. What is the purpose of the pull list in material staging?. A. To control the flow of material from the central storage location to the production storage location. B. To control the flow of material from the supplier to the production storage location. C. To control the flow of material from the production storage location to the central storage location. D. To control the flow of material from the supplier to the central storage location. 26. You are trying to create a production order and no valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question. A. The basic start date is NOT within the validity period of the production version. B. No bills of material (BOMs) are assigned to the production versions. C. The order lot size is NOT within the validity range of a production version. D. No production lines are assigned to the production versions. 27. What are prerequisites for a production version to be selected for a production order? Note: There are 3 correct answers to this question. A. The basic end date of the order must lie within the validity period of the production version. B. The basic start date of the order must lie within the validity period of the production version. C. The production quantity must only lie within the lot-size range of the routing in the production version. D. The production version must NOT be deleted. E. The production quantity must lie within the lot-size range of the production version. 28. What are some options for creating a production order? Note: There are 2 correct answers to this question. A. By setting a Kanban container to empty. B. By converting a purchase requisition. C. By partially converting a planned order. D. By setting a Kanban container to full. 29. Which of the following is a scheduling method for a production order?. A. Determination of basic dates. B. Lead time scheduling. C. Key date scheduling. D. Determination of delivery date. 30. For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question. A. The consistency check must be performed. B. The assigned routing and bill of material (BOM) must have the same validity period. C. The assigned routing and bill of material (BOM) must be valid in the entire validity period. D. The deletion flag must NOT be set for the bill of material (BOM) or the routing. E. The lot size range must be within the lot size range of the assigned routing. 31. What are some options for creating production orders without using trigger points? Note: There are 2 correct answers to this question. A. In make-to-stock production, confirmation of yield for sub-assembly triggers the creation of a production order. B. In assembly production, confirmation of scrap triggers the creation of a production order. C. In assembly production, a sales order triggers the creation of a production order. D. In make-to-stock production, you can manually create production orders. 32. During production order creation, several valid production versions are found. How does the system choose the production version?. A. Planned order or material number. B. Alphanumeric or quota arrangement. C. Validity period or sales order. D. Lot size or material cost. 33. How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question. A. By capacity planning. B. By order confirmation. C. By order release. D. By mass processing. 34. You want to create a production order. What methods can you use? Note: There are 2 correct answers to this question. A. Create in Kanban process. B. Convert a purchase requisition. C. Create by order release. D. Create without material. 35. Which settings can you make in a production scheduling profile? Note: There are 3 correct answers to this question. A. Automatic goods receipt on confirmation. B. Automatic release on order creation. C. Automatic print on order creation. D. Automatic goods issue on confirmation. E. Default order types. 36. Which of the following are scheduling time elements for a production order? Note: There are 3 correct answers to this question. A. Float before production. B. Transit time. C. Load time. D. Queue time. E. Setup time. 37. Which of the following would you recommend as SAP's strategic Sales and Operations planning tool?. A. Advanced Planning. B. Integrated Business Planning. C. Flexible Planning. D. Standard Sales and Operations Planning. 38. What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question. A. Market intelligence. B. Past quotation quantities. C. Past sales order quantities. D. Past production planning quantities. E. One-off events. 39. What will happen in the MRP run if you have created a new MRP-relevant material that supports both in-house production and external procurement?. A. The MRP run starts with external procurement. B. The MRP run starts with in-house production. C. The MRP run does NOT consider the material; it has to be planned interactively. D. The MRP run plans the material only if a quotation has been maintained. 40. What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question. A. Requirements type. B. Order type. C. Requirements profile. D. Planning strategy. |