41. When can you maintain the batch characteristic values in SAP S/4HANA? Note: There are 2 correct answers to this question. A. When you record inspection results. B. When you post the goods receipt. C. When you execute batch determination. D. When you release the batch.

42. How do you assign resources in a master recipe with operations and phases?. A. You assign resources to the sub-operations. B. You assign resources to the operations. C. You assign resources to the header of the master recipe. D. You assign resources to the phases.

43. Your company manufactures materials whose characteristics differ for each manufacturing process. Which application do you choose in SAP S/4HANA to track and use this information in all areas of logistics?. A. Process order management. B. Engineering change management. C. Quality management. D. Batch management.

44. Which options do you have to post goods receipt for a process order? Note: There are 2 correct answers to this question. A. You post the entire manufactured quantity to multiple batches if the product quality changes during production. B. You post the entire manufactured quantity to one batch if the product quality remains consistent during production. C. You post the entire manufactured quantity to multiple batches if the product quality remains consistent during production. D. You post the entire manufactured quantity to one batch if the product quality changes during production.

45. You want to verify that the properties of a component batch align with the required properties of the raw material intended for a specific process order. What function do you use to accomplish this?. A. Batch number assignment. B. Batch determination. C. Batch where-used list. D. Batch information cockpit.

46. You use the Finite Scheduling - with Reverse planning strategy and want to allow scheduling in the past. How can you parameterize this in the strategy profile?. A. Specify a negative opening period. B. Specify a negative PP/DS horizon. C. Specify a negative planning horizon. D. Specify a negative offset time.

47. What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question. A. Scheduling agreement schedule line. B. Planned order. C. Purchase order. D. Production order.

48. What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?. A. An operation is scheduled as close as possible to the desired date. B. To create a slot, neighboring operations are moved in both planning directions. C. Operations on multi-resources are planned finitely in a sequence. D. Sequencing on multi-activity resources is automatically updated during planning.

49. Your production planners are supposed to execute planning only for specific resources. What do you use to achieve this in Advanced Planning (PP/DS)?. A. A propagation range. B. A planning group. C. A work centre hierarchy. D. A planning area.

50. How can you achieve a feasible production plan when there are capacity constraints? Note: There are 3 correct answers to this question. A. Reduce the planning time interval. B. Form optimum sequences to reduce setup times. C. Execute an infinite production planning run for the critical resources. D. Increase the capacity supply in a time-phased interval. E. Determine a time period with available capacity on the planning board.