What is the valid sequence of key activities in production order processing? Please choose the correct answer. Creation, staging, release, material withdrawal, confirmation Creation, staging, release, material withdrawal, confirmation Creation, scheduling, release, material withdrawal, confirmation Creation, release, scheduling, material withdrawal, confirmation.
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? There are 3 correct answers to this question SAP Field glass SAP Concur SAP SuccessFactors SAP Ariba.
Your customer is using storage location is in SAP ECC and wants to switch to SAP S/4HANA. What do you have to consider? Please choose the correct answer. You have to set one MRP area for every storage location. MRP Live does NOT support storage locations, but classic MRP still does. Storage location MRP is replaced by MRP area functionality. Storage locations are NO longer supported.
Which elements are included in the structure of the batch where-used list? There are 3 correct answers to this question. Purchase orders Planned orders Transfers from batch to batch Stock transfers Collective orders.
Which of the following elements does the MRP run take into account? There are 2 correct answers to this question. Sales orders Planned independent requirements Shipments Material documents.
An issue storage location was NOT found through the work center, bill of material (BOM) item, or material master. What determines whether the storage location can be derived from the production version? Please choose the correct answer. Plant Data MRP Group MRP Profile MRP Controller.
You want to schedule an order in the graphical planning board. What are valid planning directions? There are 2 correct answers to this question. Infinite sequencing Squeezing in Backwards Forward with reverse.
What is the correct sequence of the following Activate methodology phases? Please choose the correct answer. Prepare, Realize, Iterate, Continuous Improvement Validate, Realize, Test , Deploy Prepare, Validate, Test, Go-Live Prepare, Explore, Realize, Deploy.
In which data objects do you maintain the production in as the work center for repetitive manufacturing? There are 2 correct answers to this question. Routing Production version Repetitive manufacturing profile Production cost collector.
What capabilities does SAP S/4HANA embedded analytics provide? There are 2 correct answers to this question. Automatic update of story boards Strategic analysis Real time decision support Comparison of current data with historical data to identify trends.
What is the equivalent in SAP S/4HANA of the Production Data Structure in PP/DS? There are 3 correct answers to this question. Routing Production Version Bill of Material Engineering Change Record.
For which data objects do you have to set up CIF integration models in S/4HANA to use them in advanced planning? There are 2 correct answers to this question. Work center Material master Contract Production plant.
What are main innovations in manufacturing in SAP S/4HANA? There are 3 correct answers to this question. Flow manufacturing Rough-cut capacity planning Monitor Production Orders Fiori app Lock-free inventory movements Material Coverage Fiori app.
Which time elements can be reduced by a reduction strategy? There are 3 correct answers to this question. Move time Queue time Goods receipt processing time Float after production Wait time.
When do you recommend the use of repetitive manufacturing? There are 2 correct answers to this question. Low product complexity High product complexity High product stability Low product stability.
Which capabilities does the Alert monitor have? There are 3 correct answers to this question. Automatically send alerts with Alert Notification Engine Automatically reschedule in case of overload alerts Nominate time-dependent substitutes for a planner Automatically predict alerts in future planning cycles Generate alerts based on defined threshold values.
What Kanban status automatically posts goods receipt with reference to the procurement element? Please choose the correct answer. Empty Wait In use Full.
You define forecast consumption as an integral part of your Production Planning and Detailed Scheduling process. Which of the following order types consume the forecast? There are 2 correct answers to this question. Purchase order Dependent demand Planned order Sales order.
Which task list types can have parallel sequences? There are 2 correct answers to this question. Reference operation sets (S) Routings (N) Master recipes (2) Rate routings (R).
Which of the following objects can you release so that the business transactions for process order execution and process management can be executed? There are 2 correct answers to this question. Individual phases Individual process instructions Individual operations Individual control recipes.
Which of these are layers in SAP Best Practice content? There are 3 correct answers to this question. Configuration guides Process diagrams Solution packages Building blocks Scope items.
What is the purpose of a reporting point confirmation in repetitive manufacturing? There are 2 correct answers to this question. To determine the work in progress along the production line To provide timely updates of inventory management for the staged components To reduce the total production lead time for along production line To stage different components for a production line simultaneously.
The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA? Please choose the correct answer. Selection Method Contract Purchasing Info Record Production Version.
When the goods receipt for a finished product is posted during confirmation on a manufacturing environment, which of the following actions are also performed by default? There are 2 correct answers to this question. Staging of components for the next order in the sequence Reduction of the capacity requirements Posting of production costs to cost collector Archiving of backflush documents.
Which transaction code can you use in SAP S/4HANA to enter and display goods movements? Please choose the correct answer. MB02 MBNL MMBE MIGO.
In Demand-Driven Replenishment, materials are classified according to several criteria. What criteria can you use? There are 3 correct answers to this question. Goods issue value Minimum order quantity Usage in bill of materials Demand variation Average daily usage.
Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA? There are 2 correct answers to this question. 100% check Simultaneous First in first out (FIFO) By usage probability.
A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR? There are 2 correct answers to this question. Operation control key Scheduling margin key Confirmation profile Production scheduling profile.
What are examples of assignment objects you can maintain in the Engineering Workbench? There are 3 correct answers to this question. Component assignment Routing to sequence assignment Material to production version assignment Material to routing assignment Material to bill of materials (BOM) assignment.
Your customer complains about incorrect duration for production order operations. What time elements could cause the issue? There are 3 correct answers to this question. Queue time Move time Floating time Tear down time Processing time.
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? There are 2 correct answers to this question. Add the agreement to the quota arrangement and mark it for MRP relevance. Set the creation indicator for purchase requisitions on the initial screen of the MRP run. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run. Add the agreement to the source list and mark it for MRP relevance.
What generates capacity requirements in a process order? Please choose the correct answer. Activities Phases Operations Resources.
Which document is skipped when SAP EWM is embedded in SAP S/4HANA? Please choose the correct answer. Warehouse order Outbound delivery request Warehouse task Outbound delivery order.
What are uses of the low- level code assigned to each material? There are 2 correct answers to this question. It is used in MRP to determine the sequence in which materials are planned. It is used by ATP to determine the priority of alternative components. It is used by engineering to identify sub items in engineering bill of materials (BOMs). It is used by product costing to determine how costs are rolled up.
How would you define pegging in the context of Advanced Planning? Please choose the correct answer. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing? Please choose the correct answer. The planned order's components are copied o the picking list. The planned order generates capacity requirements. The planned order is converted a production order. The planned order's component availability is checked.
Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What is the impact of this decision? There are 3 correct answers to this question. Net requirements calculation is sales order-specific. Sales order-specific planning run is required. Production orders are created with sales order reference. Storage location MRP areas are required. Sales order-specific stock is created.
What are some of the advantages of using Kanban? There are 2 correct answers to this question. Replenishments are based on centralized planning Replenishments are created close to the actual need It is mostly accomplished by manual postings It is a simplified form of production control.
Which advanced functionality has been embedded in SAP S/4HANA? There are 3 correct answers to this question. Available-to-promise Demand planning Supply Network Planning Capacity planning Backorder processing.
In Make-to-order production, which field controls whether the components will be planned as sales order specific stock? Please choose the correct answer. The Planning Strategy of the finished product The Individual/Collective indicator of the component The MRP Type of the component The item category of the component in the BOM.
A planner updated a production order status from partially confirmed “PCNF” to technically completed “TECO” by mistake. What impact would this have to The production manager can still see the capacity requirements The production operator cannot enter additional confirmations The warehouse clerk still carry out goods issue transactions The buyer can still see component reservations.
How can you avoid order proposals for planned independent requirements with dates in the past? There are 2 correct answers to this question. Use a planning strategy with requirements consumption Set the requirements reduction indicator in the requirements class Maintain adjustment parameter in the MRP group Reorganize planned independent requirements.
Which SAP solutions are part of the Digital Value Network portfolio? There are 3 correct answers to this question. SAP Field glass SAP Hybris SAP Human Capital Management SAP Visual Enterprise Concur.
How can you limit the number of master data objects to be created when the manufacturing process is the same for many different products? By creating routings with parallel sequences By assigning the same production version to different materials By creating routings with alternative sequences By assigning different materials to the same routing.
Which of the following apply to MRP Live? There are 2 correct answers to this question. The BAdIs for classical MRP also apply to MRP Live. The definition of the planning scope is more flexible. The sequence of planning materials is calculated across plants. Planned orders need to be converted to purchase requisitions for externally procured materials.
Which material-specific information can be transferred to a transportation lane in PP/DS? There are 3 correct answers to this question. Production versions Special procurement keys Quota arrangements Outline agreement Purchasing info records.
Which of the following business processes are controlled by production order typedependent parameters? There are 2 correct answers to this question. Implementation Engineering change management Inspection during production Planning.
During planning you are facing an overload situation on a resource. Which activities do you consider to create a feasible production plan? There are 3 correct answers to this question. Use a bucket-oriented capacity check Use optimization with respect to set-up times Use multilevel MRP run for the products on the resource Use DS heuristic “Schedule Sequence” Use rescheduling with an alternative mode.
You are transferring data from SAP S/4HANAlo embedded PP/OS. What master data objects are mapped to a location? There are 3 correct answers to this question. Plant Work center Supplier Customer Warehouse number.
A material in your company is planned with planning strategy 70 (Planning at assembly level). The consumption mode has been set to backwards with a consumption period of 12 days. Starting from when are the 12 days counted backwards? Please choose the correct answer. From the planned independent requirement date of the material From the requested delivery date of the related finished good From the availability date of the related finished good From the dependent requirement date of the material.
In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run? There are 2 correct answers to this question. Use a specific material status. Use a specific MRP controller. Use a specific MRP type. Use a specific material group.
What are some of the SAP Fiori user types? There are 3 correct answers to this question. Expert Employee Developer Occasional Business partner.
The material master of your finished product contains MRP type “PD”. You set a manual firming date in the stock requirements list. Which of the following will firm planned orders” There are 2 correct answers to this question. Creating a planned order within the planning time fence Setting a planning time fence in the Material Master Record Assigning a production scheduling profile Manually changing the quantity of a planned order.
In which customizing activity do you set up automatic routing selection for production orders? Please choose the correct answer. Define production scheduling profile Define scheduling parameters for production orders Define order-type-dependent parameter Define selection profiles.
In order to use strategy 70 – Planning At Assembly Level, what order field must be set besides the planning strategy? Please choose the correct answer. Dependent Requirements indicator Mixed MRP indicator Individual/Collective Indicator Storage Location MRP Indicator.
Which process order function uses a resource network? Please choose the correct answer. Capacity leveling Resource selection Capacity planning Resource scheduling.
Where can you find the latest in version of the Simplification List for SAP S/4HANA? Please choose the correct answer. SAP Help Portal SAP Solution Manager 7.2 SAP Best Practices Explorer SAP Support Portal.
How can you set up the supply source for the SAP Kanban process? There are 3 correct answers to this question. Using run schedule quantities for in-house production Using stock transfer reservations for stock transfer Using purchase orders for external procurement Using quotations for internal and external procurement Using purchasing costs for automated source prioritization.
In a first step you have created master recipes. In which sequence are the additional objects created? Process order Control recipe PI sheet Process message Control recipe Process order PI sheet Process message Control recipe Process order Process message PI sheet.
You need to model goods receipt processing time in Detailed Scheduling. Which modelling options do you have? There are 2 correct answers to this question. Model a resource inbound in the location master. Model a separate resource in the production data structure. Model a transportation resource in the location master. Model a handling resource in the location master and goods receipt time in the mater all master.
What steps are possible in a PP/DS production planning run? There are 3 correct answers to this question. Backorder processing Optimization Detailed scheduling functions Heuristics Demand consumption.
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks? Please choose the correct answer. Use the batch information cockpit. Use batch determination. Use the material staging report. Use the material where-used report.
You want to represent setup time as a graphical object in the Detailed Scheduling Planning Board. Which actions are needed? There are 2 correct answers to this question. Run setup minimization heuristics or optimizer. Create and assign a new graphical object for setup time in the planning board. Create and assign setup group/setup keys in the production data structure. Create and assign a setup matrix with setup transition time to the resource.
Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider? There are 2 correct answers to this question. The display template for material numbers applies to all clients. The number of leading zeros for internal numbers is client-specific. In Customizing you can decide by material type whether to use the long material number. The maximum mater all number length is 40 for external numbers and 18 for internal numbers.
What are prerequisites for using batch derivation? There are 2 correct answers to this question. Batch where-used list Receiver-sender relationships Batch determination selection conditions Process instructions.
The planning strategy requires the entry of planned independent requirements at the subassembly level, so the in-house production of this component can be triggered before a finished goods sales order is received? Please choose the correct answer. Planning without final assembly Gross requirements planning Planning at assembly level Planning with final assembly.
You are using the document management system (DMS). Where should the DMS document links be assigned, to have them automatically copied to production orders? There are 2 correct answers to this question. Material master Bill of material Routing header Work center.
In which of the following master data objects can you define the production order default storage location for a material component? There are 2 correct answers to this question. BOM, in the item for the material Work center, in the production supply area Routing, in the component allocation Material master of the finished product.
What are the three transition scenarios for an S/4HANA implementation? There are 3 correct answers to this question. New implementation System upgrade System conversion System activation Landscape transformation.
What is the sequence of the five steps of Demand-Driven Replenishment in SAP S/4HANA? Please choose the correct answer. Analytics, replenishment planning, replenishment execution, buffer positioning, buffer sizing Analytics, buffer positioning, replenishment planning, buffer sizing, replenishment execution Analytics, buffer positioning, buffer sizing, replenishment planning, replenishment execution Analytics, buffer positioning, replenishment planning, replenishment execution, buffer sizing.
What are the advantages of the new MRP Live in SAP S/4HANA compared to the classic MRP from SAP ECC? There are 2 correct answers to this question. MRP Live writes MRP lists during the run. MRP Live optimizes multi-level make-to-order planning. The MRP Live planning scope is more flexible. MRP Live reads and writes data in parallel threads.
How can you limit the validity of a bill of material (BOM)? There are 2 correct answers to this question By plant By industry By period By mater al type.
Which material master data can you copy when you use the Copy Material program (transaction MMCC, Material Master Copier) to create new materials? There are 2 correct answers to this question. Storage location data Warehouse number data MRP area data Production version data.
In which data object is the production line (Repetitive manufacturing relevant work center) maintained? Please choose the correct answer. Bill of material Cost collector Production version Repetitive manufacturing profile.
Which functional capabilities does the Detailed Scheduling Board have? There are 2 correct answers to this question. Enter time-ticket confirmation for production orders Change planned order quantities Undo for drag & Drop planning activities Change sales order quantities.
A material has been set up as a phantom assembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material (BOM)? Please choose the correct answer. Change the explosion type of the phantom assembly in the BOM. Change the item category of the phantom assembly in the BOM. Change the special procurement key of the phantom assembly in the BOM. Change the phantom item indicator for the phantom assembly in the BOM.
The SAP Kanban procedure could be used to trigger which of the following kinds of replenishment? There are 2 correct answers to this question. Subcontracting Vendor consignment In-house production Stock transfer.
Which of the following functions can be performed when the production order has the status “Created” (CRTD)? Please choose the correct answer. A user can schedule a background job to release production orders (transaction COOIS). A user can trigger material staging via mass processing (transaction COHV). A user trigger printing of shop floor paper manually (transaction CO02). A user trigger material availability check via mass processing (transaction COHV).
You want to procure your material components based on a forecast for the finished material derived from historical sales. When customers order, you produce the finished product and reserve it for that particular order. Which is the appropriate planning strategy to use? Please choose the correct answer. 50 Planning without final assembly 20 Make to order production 30 Production by lot size 40 Planning with final assembly.
What are benefits of the Engineering Workbench? There are 2 correct answers to this question. Undo/redo functionality of planned changes Detailed selection of bill of materials (BOM)items and operations Simulation of planned changes for costing and mater all requirements planning Simultaneous processing of different bill of materials (BOM) items and operations.
What does it mean for the production planner when MRP works with infinite capacities? Please choose the correct answer. MRP assigns capacity requirements automatically to work center is with the earliest available capacity. MRP creates capacity requirements only if the work center has sufficient capacity. MRP assigns capacity requirements automatically after the last scheduled order on a work center. MRP creates capacity requirements without checking the capacity of a work center.
What are the possible categories for the Business Partner master data object in SAP S/4HANA? There are 3 correct answers to this question. Vendor Group Person Customer Organization.
What new technology is used in SAP S/4HANA Embedded Analytics? Please choose the correct answer. HANA Live Smart Business Cockpit Multidimensional Reporting client (MDRC) ABAP Managed Core Data Services (CDS).
Where does the system check master data selection settings during the creation of planned orders and production orders? There are 3 correct answers to this question. In the routing In the production version In the production order type In the bill of materials (BOM) In the MRP controller.
You have a quality control check to avoid using a high-value component tin faulty materials in subsequent assembly operations. How do you account for potentials crap of the high-value material? Please choose the correct answer. Enter the operation scrap and set the net indicator in the component of the bill of mater al of the assembly. master of the assembly and set the net indicator in the routing operation where the component is used Enter the component scrap in the component of the bill of material of the assembly and leave the net indicator initial in the bill of material. Enter the assembly scrap in the material master of the component and set the net indicator in the component of the bill of material of the assembly. Enter the component scrap in the material.
The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings? Please choose the correct answer. Material Master –> MRP Group –> Plant Settings MRP Group –> Material Master –> Plant Settings Material Master –> Plant Settings –> MRP Group Plant Settings –> MRP Group –> Material Master.
You want to integrate an existing planned order into Advanced Production Planning. Which report do you use? Please choose the correct answer. /SAPAPO/CREATE_LOCATION /SAPAPO/CURTO_CREATE /SAPAPO/PPDS_DELTA_ORD_TRANS /SAPAPO/UPD_LOC_SP_PL.
Which of the following is used by the MRP Live planning run in SAP S/4HANA? Please choose the correct answer. Net change planning Planning horizon Parallel processing across servers MRP list.
When can the material availability check occur automatically in a production order? There are 2 correct answers to this question At order confirmation At order creation At order release At order settlement.
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Make-to-stock production (10) Planning with final assembly (40) Planning without final assembly (50) Make-to-order production (20).
Advanced Planning uses master data and transaction data from SAP S/4HANA. In which data objects can you set the advanced planning flag? There are 2 correct answers to this question. Material Plant Work center Production version.
How can Production Planning and Detailed Scheduling (PP/DS) enhance the standard planning functionality? Please choose the correct answer. By providing replenishment proposals with exact times By providing cross-plant planning and deployment By providing future demands from demand figures in the past By providing multilevel material requirements planning Use a bucket-oriented capacity check Use multilevel MRP run for the products on the resource.
Which of the following are capabilities of multidimensional reporting in SAP S/4HANA embedded analytics? There are 3 correct answers to this question. Drilldown Sort Forecast Filters Scheduling.
What data processing steps are obsolete if you use SAP S/4HANA Analytics? There are 2 correct answers to this question. Online analytical processing (OLAP) Pre computed aggregation views Extract on, transformation, and loading (ETL) Online transaction processing (OLTP).
At the end of the MRP run you receive the exception message “Reschedule In Operation”. What caused the message to be generated? Please choose the correct answer. The requirements date occurs before that of a firmed planned receipt A firmed planned receipt cannot be rescheduled The requirement no longer exists The requirements date occurs that of a firmed planned receipt.
Where can you maintain consumption mode and consumption periods for planning strategies? There are 2 correct answers to this question. In the plant parameters In the requirements class In the MRP group In the material master.
You are using heuristic SAP_ERP_001. Which of the following criteria are included in the automatic source determination logic when a planned order is created? Please choose the correct answer. Component availability Delivery date Costs Quota arrangement Vendor rating.
The setup time on the production line to produce a material is extensive. You would like to avoid multiple setups and limit the production of the material based on a planning calendar. Which type of lot size procedure should you use to accomplish this? Please choose the correct answer. Minimum lot sizing Fixed lot sizing Exact lot sizing Periodic lot sizing.
How does the new Inventory Management Data model contribute to the reduction of the data footprint? There are 3 correct answers to this question. By eliminating material master tables By eliminating fields for different stock types By eliminating hybrid tables By eliminating inventory history tables By eliminating inventory tables 40 Planning with final assembly.
When would you use reporting point backflush in repetitive manufacturing? There are 2 correct answers to this question. When goods issues can wait for final confirmation You require an up-to-date inventory for components When you need to determine the work in progress For production lines with short lead times.