1.How can you plan individual persons in internal activities? (2 correct) – resources. -use planning with multiple resource scheduling (MRS). -use business planning and consolidation. -use a personnel number instead of a work center. -use workforce planning.

2.       Which of the following data can be maintained in a std network? (3 correct) – Pr. Structure. -basic dates for activities. -document info records. -relationships. -internally processed activities. -material components.

3.       For which objects can billing plans (=invoice) be created? (2 correct) – Revenues/Payments. -WBS Elements. -sales order items. -milestones. -project definition.

4.       You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this? – Revenues/Payments. -The manual hierarchical revenue planning will be displayed only if expert mode is activated. -The manual hierarchical revenue planning has no reference to cost elements. -Cost element reports can display costs but not revenues. -Cost element reports display integrated planning only.

5.       You have created an internally processed network activity and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? (3 correct) – Cost/Budgets. -The formula for costing in the work center is incorrect. -the activity output price for the activity type and cost center assigned to the work center is not maintained. -The duration is missing in the activity. -The Determine Costs indicator in the network header rules out planned cost calculation. -Integrated planning for the network is active.

7.       Which features are supported in the project planning board that are not available in the Schedule Project app? (2 correct) – Dates. -create project elements. -configure displayed attributes in the project tree. -Reschedule project. -choose and display forecast dates.

8.       Which object is relevant in assembly processing to create an assembly order for the SD document? – Pr. Str. -Project profile. -Item category. -Requirement class. -Control key.

9.       How can you record external service activities with service master data? (2 correct) – Resources. -Confirm the network activity for external service. -Confirm the activities in the Cross-Application Time Sheet (CATS). -Post a goods receipt in the goods movement application (MIGO). -Create a service entry sheet.

10.   You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates? – Dates. -Activity. -Network header. -Milestone. -Activity element.

11.   The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element? – Pr.Str. Calculation of actual values. Goods receipt for purchase order. Creation of purchase orders. Activity allocation.

12.   What is the reason for assigning billing plans in customer projects? – Revenues / Payments. -Billing plans are prerequisites for quotation creation. -Billing plans are used for revenue planning. -Billing plans are copied automatically to the sales order item. -Billing plans enable the billing process to be carried out.

13.   What PP/DS master data is necessary for using pp/ds? (2 correct) – Proj. Str. -location. -material. -production version. -resource.

14.   Which of the following is visible in the project planning board? (2 correct)- Proj. Str. -relevant purchase orders. -Capacity requirements. -Maintenance orders assigned to an activity. -Production orders assigned to WBS elements.

15.   What could be a reason to use expert mode in the valuation method for results analysis? (2 correct) – Revenues/Payments. -Billing WBS elements belonging to different company codes. -Assignments of different accounts for postings to financial accounting. -Usage of different line Ids. -Results analysis dependent on user status.

16.   Which organizational structures are required for network activities? (2 correct) – Resources. Controlling area. Company code. functional area. business area.

17.   How can you allocate costs from a claim to a project? (2 correct) – Costs/Budget. -assign a network activity. -manually create an internal order. -implement a Badi. -assign a WBS element.

18.   Float time is calculated during scheduling. Which of the following statements about float time are correct? (3 correct) – Dates. -Float time can be negative. -Activities with the time constraint "Must start on" always have a negative float time. -The float time of WBS elements is calculated by extrapolation. -By default, critical activities have a float time, which is less than or equal to zero. -The maximum size of a free float is as large as the total float of an activity.

19.   Which of the following actions can transfer actual costs for external processing?. -Saving a supplier invoice. -Saving a service entry sheet. -Saving a goods receipt. -Saving a purchase order.

20.   A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? (2 correct) - Reporting. -Resource reports. -Cost element reports. -Structure information system reports. -Hierarchical reports.

21.   How are earliest dates and latest dates of activities schedule?– Dates. -Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling. -Earliest dates are scheduled forward and the latest dates backward by scheduling. -Earliest dates and latest dates are scheduled by forward scheduling. -Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.

22.   You want to allocate overhead rates (= γενικάέξοδα) to a WBS element. What must you assign to the WBS element?– Cost/Budget. Settlement rules. Costing Sheet. overhead key. Results analysis key.

23.   What are some of the advantages of using project simulations? (3 correct) – Pr. Str. -Project simulations allow posting of actual data. -Project simulations can be created without using an operational project as a template. -Project simulations can be used to plan structures and costs. -Project simulations can create purchase requisitions. -Multiple project simulations can be used simultaneously.

24.   You used reductions to reduce the scheduled duration of all internally processed activities in your project. However, the duration did not change after overall network scheduling. What do you check? (2 correct) – Dates. -If the maximum reduction level is less than 100. -If the reduction strategy is set in the network header. -If the reduction strategy is set in each activity. -If the appropriate reduction type is set in the parameters for network scheduling.

25.   Budgeting is implemented for projects. The budget has been adjusted several times. What standard report types can provide info about adjustments in the budget? (2 correct) – Reporting. -Structure overviews for budget. -Cost element report on budget updates. -Line item report for budget. -Hierarchical report on budget updates.

26.   What functions are available for period end closing in SAP Project System?. -Settlement. -Milestone trend analysis. -Confirmations. -Progress analysis. -Results analysis.

27.   You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message? – Material. -Missing budget for material components. -Missing reservations for material components. -Missing material availability. -Missing authorizations to release material components.

28.   You want to use subnetworks during the project. Which of the following statements describes subnetworks? – Pr. Str. -Maintenance orders can be defined as subnetwork. -The scheduling type of a subnetwork is always copied from the superior network. -A subnetwork cannot be defined for a superior subnetwork. -Subnetworks must be scheduled separately from the superior network.

29.   Which sales documents can update planned revenues on WBS elements? (2 correct) – Revenues and Payments. -Sales order. -Billing. -Quotation. -Inquiry.

30.   How can you confirm the working hours of different work centers for a single activity? – Resources. -Create multiple confirmations for the activity and use the appropriate work center for each confirmation. -Enter direct activity allocation assigning multiple work centers. -Enter multiple work centers within a single confirmation. -Assign multiple work centers to the activity.

31.   You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain? – Dates. -Actual dates of the network activity. -Basic dates of the WBS. -Forecast dates of the WBS. -Basic dates of the network activity.

32.   A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use? – Dates. -Only capacity requirements. -Forward. -Current date. -Backward.

33.   You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item? – Resources. -The person responsible for the work center. -The person responsible for the superior WBS element. -The MRP controller for the network. -The person responsible for the network activity.

34.   Which SAP PS system does NOT support multilingual maintenance? – Pr. Str. -std WBS element. -std network activity. -operative WBS element. -operational network activity.

35.   Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? (2 correct) – Material. -The materials must allow sales order or project stock. -The exact lot size procedure must be used. -The procurement type of the material must be internal. -An MRP group must be assigned.

36.   You want to automatically prevent users from changing the original budget on a WBS after the first budgeting activity. How can you achieve this system behavior? – Costs and Budgets. -maintain a user status profile accordingly. -maintain the budget profile accordingly. -maintain the WBS accordingly. -maintain the project definition accordingly.

37.   Which report can use user-specific layouts?– Reporting. -Line item report. -Enhanced individual overview. -Cost element report. -Hierarchical report.

38.   What are the prerequisites for resource-related billing? (2 correct) – Revenues and Payments. -A dynamic item processor (DIP) profile with the appropriate settings. -Released WBS elements, activities, and/or activity elements. -A header-account-assigned network that is assigned to a sales order item. -An activity-account-assigned network that is assigned to a sales order item.

39.   Which of the following business processes do NOT lead to the booking of actual costs to an object? (2 correct) – Revenues and Payments. -Goods receipt into non-valuated project stock. -Recording of external services in the service entry sheet. -Goods receipt of a non-stock item. -Goods receipt into valuated project stock.

40.   Which statements describe planned and actual revenue for WBS elements? (2 correct) -Revenues and Payments. -Planned revenue requires a sales order assigned to a WBS element. -Planned revenue can be transferred from a sales quotation. -Actual revenue is posted via a billing plan assigned to a WBS element. -Actual revenue is posted via a billing document created from a sales order.

41.   In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?(Resources)(correct 2). -The purchase order can be updated in Goods Receipt for Purchase Order (MIGO). -The purchase order is updated automatically to match the new quantity while saving the project. -A workflow can be triggered to inform the purchasing group. -The system automatically creates a new purchase requisition with the difference to the original quantity.

42. Which of the following apply to dynamic item processor (DIP)?(3 correct)(Revenues and Payments). -Usage of cost elements is mandatory. -Sales prices are maintained in the DIP profile. -DIP is used to create a quotation. -Sources can be based on line items. -Material determination is mandatory.

43. What business transactions can be used with Project-Oriented Procurement (ProMan)?(3 correct)(Material). -Confirm production order. -Stock transfer posting. -Generate purchase requisition. -Generate delivery. -Cancel goods issue.

44. What functionality can you perform with activity elements? (Project structures). -Assign material. -Assign work centers and capacities. -Create relationships. -Schedule WBS element.

45. What are the prerequisites for delivering materials from the project? (2 correct)(Material). -A delivery document type must be configured. -A sold to party is necessary. -A shipping point is necessary. -A sales order must be created in advance.

46. Which sets of dates can be used to schedule networks?(2)(Dates). -Baseline. -Forecast. -Planned dates. -Basic dates.

47. How can the system activate requirements (such as reservations or purchase requisitions)? (2 correct)(Material). Immediately, by saving the project. Automatically, using the requirement date and the replenishment lead time. Using a standard milestone activity. When releasing a network or an activity.

48. Which of the following statements describe simulations versions? (2)(Project structures). Simulations versions can be created automatically based on user status. Simulations versions are mandatory for Milestone Trend Analysis (MTA). Simulation versions can be changed. Manually created simulation versions require a simulation version profile.

49-In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning? (Resources). Scheduling and capacity category. Scheduling and distribution key. Control key of an activity. Capacity planner group in the network header.

50- Where can you define a network as Header-Account-Assigned or Activity-Account-Assigned.(Cost and Budgets). Project profile. Parameters for the network type. Network profile. Network type.

51- Where can you activate the generation of actual capacity requirements?(Resources). Network activity. Network header. Network profile. Work center.

52- Which objects do you have to maintain to enable automatic assignment of material components to the project?(Material) (2). Material master. WBS element. Network activity. BOM item.

53- You are using budgeting and active availability control. How can availability control be activated? (Cost and Budgets)(2). Automatic activation with budget assignment. Automatic activation with assignment to an investment program. Background activation (CJBV - Activate Availability Control). Automatic activation with the first actual posting.

54- The system issues the error message that planned costs could not be calculated for an internally processed network activity. What could be possible reasons for this system behavior?(Cost and budgets)(3). The capacity requirements have not been activated for the internal activity. The work center is missing in the activity. The calculation variant is missing in the work in the network header. The costing sheet is not assigned to the internal activity. The activity type is missing in the activity.

55- Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?(Material). Set up the requirement date aligned with the activity finish date and an of set of 15 days. Set up the requirement date manually as February 5. Set up the requirement date aligned with the activity start date and an of set of 5 days. Set up the requirement date aligned with the activity start date and a negative of set of 5 days.

56- You have a project with a network and milestones. You want to plan a break off two days between the activity and its predecessor. How can you do this?(Dates)(2). Use an offset of two days for the milestone date. Use an offset of two days for the relationship of both activities. Enter an additional duration of two days in the predecessor activity. Calculate the start date of the activity and set the constraint Must Start on accordingly.

57- What do you maintain the length of the project ID key?(Project structures). Project profile. Project coding mask. Project Type. Special characters.

58- To which object can you assign a factory calendar? (Dates). Material component. Network header. Milestone. Relationship.

59- You want to use billing for a customer project. Which customizing object controls the billing of sales order items? (Revenues and Payments). Items category. Schedule line category. Requirements class. Requirements type.

60- Which of the following are valid procurement types for stock items?(3) (Material). Preliminary purchase requisition for WBS element. Purchase requisition and reservation for WBS element. Planned order. Third-party order. Reservation for WBS element.

61- An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates? (Material). The scheduling parameters for the network. The network profile. The control key. The table of MRP controllers.

62- Your customer has created networks with internal activities and generated capacity requirements. Now they want to analyze the capacity requirements of their project. Which report do you recommend? (Reporting). Structure overview. Capacity load work center view. Extended capacity evaluation. Individual overview capacity requirements.

63- Which of the following factors influence the scheduling of internal processing activities?(Dates)(3). An activated Scheduling indicator in the control key of the internal processing activity. Whether the work for the internal activity is greater than its duration. The unit (for example, hour, day) of the field Normal Duration field of the activity. The relationships between activity elements. The factory calendar in the work center used for the internal processing activity.

64- You assign milestones to WBS elements. What can you use these milestones for? (Project structures)(3). To start workflow tasks. To use trend analysis. To transfer the actual date to the billing plan. To use progress analysis. To release subordinate WBS elements.

65- Which document types can be created directly in Project-Oriented Procurement. (ProMan)? (Material) (3). Production orders. Planned orders. Reservations. Purchase orders. Outbound deliveries.

66- You are working with predefined project coding masks to create projects. You can use indicator to specify that only coded project numbers may be used with SAP Project Systems. You can shorten the project mask even then there are existing projects. You can only use numbers for a project coding mask definition. You can use the same coding mask for standard projects and operative projects.

67- You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? (2)(Resources). Maintain subordinate internal activity elements assigned to other work centers. Increase the capacities of the work center in the project planning board. Trigger automatic capacity levelling inside the project planning board. Shift activities backward or forward on the time axis where more capacities are available.

68- Which statements describe networks?(project structures)(2). A network activity can be assigned to several WBS elements. Material components can be assigned to activity elements. Relationships can be used to connect activities of different networks. A network can be activity-account-assigned or header-account-assigned.

69- What are some of the possible functions in user status profiles? (Project structures)(2). Restrict setting user status for individual users. Utilize priorities for setting the user status. Ensure user status must always be set manually. Allow business processes forbidden by SAP system status.

70- You have created a billing plan for a project. How can you ensure that the billing plan dates change automatically according to the scheduling of the project?(Dates)(2). Derive the billing plan from milestones in your project. Maintain the Fixed Date setting in the date category for billing plan type. Assign the billing plan items to the responsible WBS elements. Assign the billing plan items to the corresponding network activities.

71- How can you grant individual authorization to WBS elements and networks?(Project structures). Activate access control lists (ACL) for the user master record. Define a user status to lock business transaction Update Project. Set the system status to Lock Master Data. Activate access control lists (ACL) for the project profile and the network profile.

72- You want to set up the field selection of the screen for network activity confirmations in customizing.Which influencing fields are you able to use?(Project structures)(3). MRP controller. Data entry profile. Order type. Organizational unit. Control key.

73- The basic dates of subordinate WBS elements should be extrapolated without considering the basic dates of higher level WBS elements. What planning method for basic dates do you use?(Dates)(1). Top down. Free planning. Strict bottom-up. Bottom up.

74- When you create a service activity in your network, what data can be entered?. Service purchase order number. Overall limit (maximum value of all unplanned services). Service specification. Material master with service specification. Vendor.

75- You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?(Material)(2). The availability check for material reservation indicates missing parts. The Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to never. The material master is set to external procurement. The material is assigned to the activity as a non-stock material.

76- Which objects can be used to specify settlement rules?(Cost and Budgets)(2). Network activity for activity-account-assigned networks. Networks header for activity-account-assigned networks. WBS elements. Standard WBS elements.

77- Which planning method can prevent further rescheduling of activities?(Resources). Partial confirmation of activities. Capacity leveling. Capacity requirements activation. Workforce planning.

78- You want to establish costing for WBS. Costing should not refer to cost elements. Planning of overall values. Unit costing for WBS. Easy Cost Planning (ECP) for WBS. Detailed planning WBS.

79- A service company uses project management, and they complain that the system does not prevent their project managers for exceeding their budgets. What could be possible reasons for this system behavior?(Cost and budgets)(3). Availability control is deactivated in the controlling area of the project. Workflow for availability control is not defined correctly. Availability control is deactivated in the assigned budget profile. Availability control is deactivated for the individual project. Tolerance limit is not defined correctly.

80- You are using networks and external processing activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents? (Resources). Vendor selection -> Purchase order handling -> Invoice receipt ->Purchase order monitoring -> Goods receipt. Credit limit check ->Acceptance of performed services ->Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> invoice receipt. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt.

81. A customer uses cross-company-code project with a top billing element and additional billing element underneath for each company code. Although the internal correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?. -Settle the WBS element to the highest billing element before you do the result analysis. -Split the project into different project according to each company code. -Change the so that it corresponds better to the company's organization structure. -Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

82. Your customer wants to plan and post revenues for WBS elements. What is crucial for the implementation of revenues planning and posting for WBS elements? (1). -At least one WBS element must be a billing element. -The indicator "Project type" must be set to "Customer project". -Revenue planning and billing must be activated in the corresponding network type. -A sales order item must be assigned to each WBS element used for revenue planning.

83. Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board(3 correct). -Display of production orders assigned to WBS element. -Display of plant maintenance orders for activities. -Display of project cost plan. -Display of project-relevant purchase order. -Using specific color management for Gantt Chart.

84. You are using network and internal activities in your project. You have already created a purchase requisition and the bid invitation, and have entered the quotation What is the typical sequence for the following business transactions and document. -Benefit check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoice. -Vendor selection - purchase order handing- purchase order monitoring- Benefit of services. -Check-Acceptance performed. -Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt. -Vendor selection- Purchase order handing-purchase order monitoring-Good receipt-Invoice receipt.

85. Your customer uses Progress Tracking for network components and maintains dates of events manually. They need to implement scheduling of events. What are the requisites for implement scheduling of events?. -Priority of events must be set. -Scheduling parameters for material scheduling must be set. -Events must be released manually. -Event scenarios must be defined.

86. Which of the following statements apply to project versions? (2 correct). -Project versions can be changed. -Project versions are mandatory for Milestone Trend Analysis (MTA). -Project versions can be created automatically based on user status. -Manually Created project versions always require a project version profile.

87. How can you update the degree of processing for an activity?. -By using results analysis. -By changing the activity. -By scheduling the activity. -By confirming the activity.

88. You plan double the work on each internal activity for multiple projects. What do you recommend?. -Use mass change (CNMASS) in the project system. -Double the work of each internal activity, one after another, in the project Builder. -Double the capacity in the work center. -Use mass change within the project Builder (CJ20N).

89. You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget. -Results analysis. -Easy Cost Planning. -Cost forecast. -Availability control.

90. You want to create purchase requisition for the material used in your project. However, after releasing the project, no purchase requisition has been created. What could be the reason? (2 correct). -The procurement type in the material master is set to in-house Production. -The item category of the materials is set to stock item. -The material have no material number. -The item category of the materials is set to non-stock item.

91. Which of the following is used to plan basic dates manually for WBS elements? (2 correct). -Schedule Manager. -Project Builder. -Project planning board. -Easy Cost Planning.

92. Which of the following transactions can you use to post actual cost for external processing. (2 correct). -Approval of a service entry sheet. -Posting a goods receipt. -Creating a service entry sheet. -Approval of a good receipt. -Creating a purchase order.

93. You use a WBS with network and maintenance order. You want to schedule both the network and the maintenance order. What do you have to consider?. -The maintenance orders must be assigned to WBS element. -The maintenance order s must be assigned to the same budget profile as the project definition. -The maintenance orders must be assigned as sub-networks. -The maintenance orders must be assigned to the same plant as the network.

94. The various work packages in the project are described as individual______________. Choose the correct answer. -WBS elements. -Project definitions. -Tasks. -Activities.

95. Your customer uses a tight integration between sales order and WBS with network to deliver finished and semi-finish product. What benefit do they have when using delivery from project (CNSO). -With delivery from projects you can generate goods issues for project without creating delivery documents. -With delivery from projects good receipt are automatically posted while saving. -With delivery from projects you can generate purchase requisitions for sub-contractors. -With the delivery from project you can deliver material component assigned to your network.

96. You want to enable user fields for customer project. Therefore, you create several field keys. What is the benefit of assigning a field key to the project profile?. -The field key is the default value for the WBS element and the activities too. -The tab user fields are invisible. -The field key is hard coded in the WBS element. -The field key is the default value only for the WBS element.

97.The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer. -Plant. -Controlling area. -Company code. -Planning department.

98. Which the following statement regarding networks are correct? (3 correct). -If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center. -You can assign more than one activity element to a network activity. -Capacity requirements of a network activity are reduced when the activity is confirmed. -During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity. -You can assign the same work center to more than one activity on the same network.

99. How can you search in the structure overview based on the user status? (2 correct). -By searching for the status profile. -By searching via status selection profile. -By searching via status combination code. -By searching for the individual status.

100. You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to theproject. What are the prerequisites? (3 correct). -A bill of material with sales views. -A material master with sales views. -Assignment between material and standard network. -Standard network with activities. -A production order.

101. Which of the following actions can transfer actual costs for external processing? (2 correct). Saving a supplier invoice. Saving a service entry sheet. Saving a goods receipt. Saving a purchase order.

102. You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? (2correct). You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released". You can always maintain the actual start if the WBS element has the status "Released" or "Partially released". You can always maintain the actual start and finish date of a WBS element. You can only maintain the actual start of a WBS element if the finish date is not maintained.

103. Which statement is valid regarding networks? 2correct. A network activity can be assigned to several WBS elements. Material components can be assigned to activity elements. Relationships can be used to connect activities of different networks. A network can be activity-account-assigned and header-account-assigned.

104. You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?. Network profile. Data entry profile. Project profile. Network type.

105. Which of the following statements are true? (2 correct). You can map a project using only one WBS or one network. You can also represent a project using a WBS and one or more networks. You can create a project based on a Activity. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.

106. You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?. Enter an offset of -18 days to the finish date of the activity. Enter February 10 as fixed date. Enter 10 days as duration. Enter an offset of 10 days to the start date of the activity.

107. You want to determine the planned costs for an internally processed activity. Which data do you need (2 correct). Duration. Activity type. Work. Profit center.

108. Where do you control whether a project stock is managed as valuated or non-valuated project stock?. In the network activity. In the project definition. In the WBS element. In the material master.

109. You are working with networks and WBS elements. Which of the following statements applies. You can reassign an activity from one network to another. You can assign the network header to multiple WBS elements. You have to maintain a network profile in the project profile. You have to activate the operative indicator Account Assignment Element for WBS element with activities.

110. A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? (3 correct). The network activity is assigned to a WBS element. The network is assigned to a sales order item. The Project Stock indicator is set in the project definition (non-valuated or valuated). The material master of the component must permit project stock management. A procurement indicator must be assigned to the activity.

111. A customer works in a multilevel production environment with bill of material and routing. To avoid unnecessary stock cost, they do not want to produce. Which setup do you recommend? Cost and Budget. Assign a sales order to a project with appropriate hierarchy levels. Assign a network to a sales order. Assign Several production orders to a sales order. Assign One production order to a sales order.

112. You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder? (3 correct). Project milestone. Standard network. Standard Project definition. Project version. Project definition.

113. You want to exchange data between SAP Project System and Microsoft What interface do you use?. The EPS interface (External Project Software). No interface to Microsoft Project is available. The catalog interfaces. You do not need an interface. You can exchange data using object link.

114. Which statement regarding the creation of a new work breakdown structure (WBS element) are true? (3 correct). You can create several WBS elements per level. A new work breakdown structure must contain up to 10 levels. A WBS element of the new project can be assigned to a different project definition. WBS element can be a planning element, an account assignment element, and a billing element at the same time. The WBS structure can contain several level 1 WBS element.

115. What is the transaction code for editing the planning profile? 1 correct. OPSC. OPSB. OPSS. OPDS.

116. Resources You Want assign milestone to WBS element? For what can you use these milestone. Resources. To create standard network. To start workflow task. For trend analysis. To set an actual finish date for WBS element.

117. Which object is used to allocate the costs from a claim to the project structure?. Network activity. Internal order. Claim. WBS element.

118. How are capacity requirements determined?. a. Independent of scheduling and according to the capacity planner group. b. Using scheduling and the capacity category. c. Using the control key of an activity. d. Using scheduling and distribution key.

119. How can you define external task in your project. Note : there are 2 correct answers for this question. Resources. a. Assign a purchase order for external processing to the project definition. b. Create an external activity in a network. c. Create a service milestone. d. Create a service activity in a network.

"120. A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?". Activate availability control for the WBS elements. Define the tolerance limits on each WBS element. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing. Activate commitment management in the project definition Enter the budget in the master data of the top WBS element. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.